Field Report Thursday May 29, 2008

Thursday 29th May, 2008

Friday May, 23rd, through Thursday May 29th, 2008.

This week highs 70’s and 60’s during day, low 40’s to 50’s overnight, periods of light rain over the past weekend and occasional overnight light rain throughout the week. Occasional showers forecast for the second half of next week with highs in the 80’s.

Progress; Friday 23th to Thursday 29th May, 2008

Lot 1; footing poured, masonry on site for foundation
Lot 2; slab prep in progress garage and kitchen, living room slab poured
Lot 3; house slab complete, masonry on site for party wall
Lot 4; house slab complete, masonry on site for party wall
Lot 5; foundation masonry in progress
Lot 6: foundation masonry in progress
Lot 7; footing poured, masonry on site for foundation


Lot 8; main roof truss installed
Lot 9; main roof truss installed
Lot 10; main roof truss installed
Lot 11; main roof truss installation in progress
Lot 12: main roof truss loaded for installation
Lot 13; main roof truss loaded for installation

Lot 14; main roof truss loaded for installation
Lot 15; main roof truss loaded for installation
Lot 16; main roof truss loaded for installation
Lot 17; main roof truss loaded for installation
Lot 18; main roof truss loaded for installation
Lot 19; main roof truss loaded for installation

Lot 20; main roof truss installed
Lot 21; main roof truss installed
Lot 22; main roof truss installed
Lot 23; main roof truss installation in progress
Lot 24; main roof truss loaded for installation
Lot 25; main roof truss loaded for installation
Lot 26; main roof truss loaded for installation

Anticipated Progress next week weather permitting;

Lot 1; foundation masonry in progress
Lots 2 through 4; party wall masonry in progress
Lot 5 & 6; foundation masonry complete, fill in progress
Lot 7; foundation masonry in progress
Lot 8 through 13; main roof truss complete
Lot 14 through 19; main roof truss in progress
Lots 20 through 26; main roof truss complete

Prepared by Colin Dawson RA






Wednesday, May 28, 2008

Field Report Wednesday May 28, 2008

Mid 70's F clear, mid 50's overnight with light rain.

Lot 4 house slab complete, garage prep for pour
Lot 3 house slab complete, garage prep for pour
Lot 2 sub-slab plumbing
Lot 1 footing rebar set
Lot 5 & 6 foundation masonry in progress
Lot 7 footing excavation
Lot 8 roof truss install.
Crane loading roof truss.









Monday, May 26, 2008

Field Report Friday May 23, 2008


Lot 3 & 4 kitchen slab pour























Lot 5 & 6 prep for footing pour




Thursday, May 22, 2008

Field Report 5-22-2008

Thursday 22nd May, 2008

Friday May, 16th, through Thursday May 22nd, 2008.

This week highs 60’s and 40’s during day, low 40’s to 50’s overnight, periods of heavy rain over the past weekend and occasional rain throughout the week. Periods of rain forecast for this coming weekend and next week with highs in the 80’s.


Progress; Friday 15th to Thursday 22th May, 2008
Lot 1;
excavation in progress
Lot 2;
slab prep in progress, living room slab poured
Utility pole rot and fractured, PECO replaced
Lot 3;
slab prep in progress, living room slab poured
Lot 4;
slab prep in progress, living room slab poured
Lot 5;
layout for foundation in progress
Lot 6:
layout for foundation in progress
Lot 7;
fill stock-pile removal in progress

Lot 8;
1st and 2nd floor framing complete, no new work, roof truss delivered
Lot 9;
1st and 2nd floor framing complete, no new work, roof truss delivered
Lot 10;
1st and 2nd floor framing complete, no new work, roof truss delivered
Lot 11;
1st and 2nd floor framing complete, no new work, roof truss delivered
Lot 12:
1st and 2nd floor framing complete, no new work, roof truss delivered
Lot 13;
1st and 2nd floor framing complete, no new work, roof truss delivered

Lot 14;
1st and 2nd floor framing complete, no new work, roof truss delivered
Lot 15;
1st and 2nd floor framing complete, no new work, roof truss delivered
Lot 16;
1st and 2nd floor framing complete, no new work, roof truss delivered
Lot 17;
1st and 2nd floor framing complete, no new work, roof truss delivered
Lot 18;
1st and 2nd floor framing complete, no new work, roof truss delivered
Lot 19;
1st and 2nd floor framing complete, no new work, roof truss delivered

Lot 20;
2nd floor framing in progress
Lot 21;
2nd floor framing in progress
Lot 22;
1st and 2nd floor framing complete
Lot 23;
1st and 2nd floor framing complete
Lot 24;
1st and 2nd floor framing complete
Lot 25;
1st and 2nd floor framing complete
Lot 26;
1st and 2nd floor framing complete


Anticipated Progress next week weather permitting;

Lots 2 through 4; slab pour in progress
Lot 1; prep for footing
Lot 5 & 6; footing concrete complete, foundation masonry in progress
Lots 20 & 21; framing complete

Roof truss in progress


Prepared by Colin Dawson RA

Thursday, May 15, 2008

Union Square Project Meeting





Thursday 15th May, 2008

Monday May, 12th, through Thursday May 15th, 2008.

This week highs to low 80’s and high 40’s during day, low 40’s to 50’s overnight, periods of heavy rain over the past weekend and Monday. Periods of rain forecast for this coming weekend and next week.

Attendance/Distribution;

Harold Thomas Union Square Homes
James Thomas Union Square Homes
Dan Thomer WDC Construction
Lisa Gaffney CEDA
Michael Washington OHCD
John Paczewski PHFA
Kevin Maguire for TRF
Colin Dawson RA CDRA


Progress; Monday 12th to 15th May, 2008
Lot 1;
excavation in progress
Lot 2;
sub-slab plumbing and slab prep in progress
Lot 3;
sub-slab plumbing and slab prep in progress
Lot 4;
sub-slab plumbing and slab prep in progress
Lot 5;
excavation in progress
Lot 6:
excavation in progress
Lot 7;
to be excavated (used as fill stock-pile)

Lot 8;
1st and 2nd floor framing complete, no new work, roof truss delivered
Lot 9;
1st and 2nd floor framing complete, no new work, roof truss delivered
Lot 10;
1st and 2nd floor framing complete, no new work, roof truss delivered
Lot 11;
1st and 2nd floor framing complete, no new work, roof truss delivered
Lot 12:
1st and 2nd floor framing complete, no new work, roof truss delivered
Lot 13;
1st and 2nd floor framing complete, no new work, roof truss delivered

Lot 14;
1st and 2nd floor framing complete, no new work, roof truss delivered
Lot 15;
1st and 2nd floor framing complete, no new work, roof truss delivered
Lot 16;
1st and 2nd floor framing complete, no new work, roof truss delivered
Lot 17;
1st and 2nd floor framing complete, no new work, roof truss delivered
Lot 18;
1st and 2nd floor framing complete, no new work, roof truss delivered
Lot 19;
1st and 2nd floor framing complete, no new work, roof truss delivered

Lot 20;
house slab complete this day, 1st and 2nd floor wall panels on site.
Lot 21;
house slab complete this day, 1st floor wall panels on site.
Lot 22;
1st and 2nd floor framing in progress
Lot 23;
1st and 2nd floor framing in progress
Lot 24;
1st and 2nd floor framing in progress
Lot 25;
1st and 2nd floor framing in progress
Lot 26;
1st and 2nd floor framing in progress


Anticipated Progress next week weather permitting;

Lots 2 through 4;
slab pour in progress
Lot 1;
footing concrete in progress
Lot 5, 6 & 7;
footing concrete in progress
Lots 20 through 26;
1st and 2nd floor framing complete

Work has been in progress from October 2007, under permits issued for house construction only.

INFRASTRUCTURE:
Site infrastructure including the storm water infiltration system has received a verbal agreement with DELCORA and the City Engineer, formal approval to follow.

Submissions have been made to the Chester Water Authority (CWA) for a new water main in Union Street.

Submissions for PECO gas and underground electric service have been made.

Submissions for Verizon Fios underground service have been made, all houses will be provided with a Fios panel from which the homeowner can contract with Verizon to provide; fiber-optic telephone, internet and television service.

The project schedule to completion is dependent upon a schedule to be developed with the underground utility providers; however the Union Square Homes (USH) anticipates a sample home completed by mid-July.

PAYMENT VOUCHER:
The payment voucher prepared by WDC was reviewed and approved. Two vouchers were prepared one for the work excluding site infrastructure items, and one for site infrastructure only. The infrastructure only voucher was prepared for information only and will not be submitted for review and approval until a formal approval has been issued for the infrastructure portion of the work.

MEETING SCHEDULE:
Voucher meetings will be held each month on a Wednesday at 1:00 PM, a meeting schedule is to be issued.

The meeting was adjourned.

Prepared by Colin Dawson RA



Friday, May 9, 2008

Union Square Field Report

Monday May, 5th, through Friday May 9th, 2008.

This week highs to low 80’s and high 50’s during day, low 40’s to 50’s overnight, periods of rain Thursday and all day Friday through Saturday. Periods of rain forecast for next week.


Progress;
Lot 1; excavation in progress
Lot 2; sub-slab plumbing and slab prep in progress
Lot 3; sub-slab plumbing and slab prep in progress
Lot 4; sub-slab plumbing and slab prep in progress
Lot 5; excavation in progress
Lot 6: to be excavated (used as fill stock-pile)
Lot 7; to be excavated (used as fill stock-pile)

Lot 8; 1st and 2nd floor framing complete
Lot 9; 1st and 2nd floor framing complete
Lot 10; 1st and 2nd floor framing complete
Lot 11; 1st and 2nd floor framing complete
Lot 12: 1st and 2nd floor framing complete
Lot 13; 1st and 2nd floor framing complete

Lot 14; 1st and 2nd floor framing complete, no new work
Lot 15; 1st and 2nd floor framing complete, no new work
Lot 16; 1st and 2nd floor framing complete, no new work
Lot 17; 1st and 2nd floor framing complete, no new work
Lot 18; 1st and 2nd floor framing complete, no new work
Lot 19; 1st and 2nd floor framing complete, no new work

Lot 20; garage and living room poured prep for kitchen pour,
1st floor panels on site.
Lot 21; garage and living room poured prep for kitchen pour,
1st floor panels on site.
Lot 22; house slab complete, 1st floor wall panels on site.
Lot 23; house slab complete, 1st floor wall panels on site.
Lot 24; house slab complete, 1st floor wall panels on site.
Lot 25; house slab complete, 1st floor wall panels on site.
Lot 26; house slab complete, 1st floor wall panels on site.


Anticipated Progress next week weather permitting;

Lots 2 through 4; slab pour in progress
Lot 1; excavation complete
Lot 5, 6 & 7; excavation in progress
Lots 20 & 21 house slab complete
Lots 22 through 26; 1st floor framing in progress

Sunday, May 4, 2008

Union Square Field Report

Tuesday April, 29th, through Friday May 2nd, 2008.

This week highs to low 70’s and 50’s during day, low 40’s to 50’s overnight, periods of rain all week.
Rain over past weekend. No work on Monday. Next week highs in 70’s, showers later in week.

Progress;
Lot 1; to be excavated (excavated library basement used as sump)
Lot 2; foundation masonry complete, back-fill in progress
Lot 3; foundation masonry complete, back-fill in progress
Lot 4; foundation masonry complete, back-fill in progress
Lot 5; to be excavated (used as fill stock-pile)
Lot 6: to be excavated (used as fill stock-pile)
Lot 7; to be excavated (used as fill stock-pile)

Lot 8; 1st and 2nd floor framing in progress
Lot 9; 1st and 2nd floor framing in progress
Lot 10; 1st and 2nd floor framing in progress
Lot 11; 1st and 2nd floor framing in progress
Lot 12: 1st and 2nd floor framing in progress
Lot 13; 1st and 2nd floor framing in progress

Lot 14; 1st and 2nd floor framing complete
Lot 15; 1st and 2nd floor framing complete
Lot 16; 1st and 2nd floor framing complete
Lot 17; 1st and 2nd floor framing complete
Lot 18; 1st and 2nd floor framing complete
Lot 19; 1st and 2nd floor framing complete

Lot 20; garage prep for pour
Lot 21; garage prep for pour
Lot 23; garage pour, sub-slab plumbing in progress
Lot 24; garage pour, sub-slab plumbing in progress
Lot 25; garage pour, kitchen/den slab prep for pour
Lot 26; garage pour, kitchen/den slab prep for pour

Anticipated Progress next week weather permitting;

Lots 2 through 4; sub-slab plumbing in progress
Lots 8 through 13; 1st and 2nd floor framing complete
Lots 14 through 19; WDC framing punch-list items
Lots 20 through 23; garage pour, sub-slab plumbing in progress.
Lots 24 through 26 1st and 2nd floor framing in progress