Wednesday, July 23, 2008

Field Report Wednesday July 23, 2008

Wednesday July 23, 2008
High 80's F during day, 70's F overnight, thunderstorms overnight with thunderstorms forecast next few days.

Lots 1 through 7:
Windows installed.
Rough mechanical in progress
Lot 6 & 7 roofing base sheet installed, shingles on site.

Lots 20 through 26:
Windows installed.
Framing punch list items in progress.

Lots 20 through 25, 3rd Street at Jeffery Street
Lots 26 through 20, 3rd Street at Yarnall Street
Lots 7 though 1, 4th Street at Yarnall Street.
Lots 1 through 7, 4th Street at Jeffery Street
Lots 20 through 26, 3rd Street rear
Lots 1 through 7, 4th Street rear
Lots 7 through 1, 4th Street rear.

Monday, July 21, 2008

Field Report Monday July 21, 2008

Monday July 21, 2008
Low 90's F during day, 70's F overnight, isolated thundershowers in the region but none reported in the coastal zone below the piedmont rise.

On site discussion with;
Dan Thomer: WDC
Harold Thomas: Union Square Homes
Jihad Ali: Union Square Homes
Colin Dawson: Colin Dawson RA

Masonry wall Reinforcing:
Dan prior to this meeting discussed masonry wall reinforcing with the masonry sub-contractor; placement of reinforcing has been inconsistent, and is suspect at all locations 1st floor walls, and 2nd floor lots 20 through 26 and lots 5 through 7.

Dan reports "John" his assistant observed reinforcement placement at walls lots 3 to 2, and 4 to 3, and will be onsite to observe reinforcement placement for all subsequent walls.

To provide additional lateral support for masonry walls, the epoxy anchor bolts required in the permit set to secure framing to masonry will be extended where possible and installed as through bolts with oversize galvanized fender bolts on the wall exterior.

Framing punch list lots 20 through 26:
Exterior strap ties 1st to 2nd floor panels, and gable panels in progress.
Wall panel to wall panel nailing in progress.
Wall panel sill plate bolts in progress.
Triple stud at triple joist on bearing wall (a few not done, stud may be installed at 90 deg to wall studs to clear in place electrical wire).
Top hung joist hangers at triple joist to masonry wall ledger, not done.
Top hung joist hangers at stair well double stud, not done.

5/8" type "X" drywall:
All drywall will be 5/8" type "X" for superior finish quality, the 1/2" drywall band at kitchen ceiling/garage wall will be backed-up with 5/8" drywall.
WDC requested and Colin Dawson RA approved 5/8" type "X" drywall to garage ceiling and delete drywall to garage roof void/house 2nd floor wall.

Lot 3 to 2 masonry party wall 2nd floor in progress.
Lots 8 through 13 masonry delivered.
Lot 20 exterior strap ties in place.

Friday, July 18, 2008

Field Report July 17, 2008

July 17, 2008
Mid 90's F during day, 70's F overnight, isolated thunderstorms
90's F forecast for next 5 days with isolated thunderstorms.

Lots 1 through 7, 4th Street at Jeffery Street 7-17-2008
Lots 7 through 1, 4th Street Rear, 7-17-2008
Lot 3 to 4 partywall, top of bond beam, no rebar, 7-17-2008
Party wall lot 3 to 4 scaffold set
Lot 3-4 partwall masonry in progress 7-15-2008
Damaged 4" sanitary stack
Lot 24, sheathing to be replaced.

Lot 26, Jeffery Street wall, sheathing to be replaced.

Tuesday, July 15, 2008

Field Report Tuesday July 15, 2008

Tuesday July 15, 2008
Low 90's F during day, high 60's overnight. Rain on Monday, forecast dry and 90's for the week.

Lot 1 through 7

Masonry party wall complete 7-6, 6-5, 5-4 and 4-3 scaffold set.

Lot 20 through 26

Rough mechanicals in progress.

Framing punch list items, also discussed with Tom Heisner L&I;

- Install exterior strap ties 1st to 2nd floor wall panels at each 3rd stud
- Install exterior strap ties 2nd floor wall panel to front gable and end gable over garage, at each 3rd stud.
- Fully nail, shim and block, wall panel to wall panel throughout, including at outside corners and garage wall to house wall.
- Install jack studs at living room/kitchen opening header.
- Install triple stud at triple joist bearing on frame walls.
- Install top hung hangers at all mutiple joist locations including triple to ledger and at stairwell, solid block as previously noted where single joist is close to triple joist and use an oversize top hung hanger.
- Through bolt built-up joist beams.
- Epoxy anchor bolt front and rear walls, 1st and 2nd floor and garage walls to masonry wall,
- Epoxy anchor main and garage roof truss to masonry wall
- Check all sill plate to masonry foundation bolts, install all nut and washer tight, install epoxy anchor bolt where anchor bolts missing including within 12" from end of each panel and not less than 48" o.c.
- Garage to house wall is a 1hr rated wall, 5/8" type "X" gwb both sides, the gwb band at ceiling framing in kitchen and laundry was installed as 1/2" gwb. Overlay or replace with 5/8" type "X" and fire tape above ceiling.
- Drywall installation must include 5/8" type "X" at garage to kitchen, laundry, 2nd floor bedroom and 2nd floor bathroom, and on garage side including over the truss adjacent to frame house wall, and 1st truss bay underside of roof sheathing.

-Lot 24; 4" sanitary stack damaged above slab, cut out and replace.

Chester L&I to be call for inspection of exterior strap ties before house wrap installed.

Friday, July 11, 2008

Field Report Friday July 11, 2008

Friday July 11, 2008
High 80's clear, 70's overnight.

Lots 20 through 26;
Rough mechanicals in progress

Lots 1 through 7;
Main roof sheathing complete, front gable in progress
Masonry partywall complete lots 7-6 & 6-5, scaffold set for lot 5-4.

Lots 1 through 7, 4th Street at Jeffery 7-11-2008
Party wall lots 7-6 & 6-5, 4th Street rear 7-11-2008
Party wall lot 7-6, 4th Street rear in progress, 7-10-2008