Mid 80's F during day, dry and clear, 60's F overnight.Isolated showers and thunderstorms forecast for next 5 days.

Siding complete except garage front lots 20 through 26
Brick front complete lots 20 through 23
Floor leveling complete lots 20 through 26
Trim in progress lots 20, 21 & 22
Insulation complete and drywall on site lots 23, 24, 25 & 26


Lot 23
Lot 22
Lot 21


Lot 20
Lots 20 through 26, 3rd Street
PECO gas in progress Jeffery Street, 3rd to Union
LOt 26 through 20 rear
Lot 26
Lot 25
Lot 24
Lot 23
Lot 22
Lot 21
Lot 20

Sunday, August 17, 2008

Field Report Friday August 15,2008

Friday August 15, 2008


Mid 80'F during day, 60's F overnight, clear, rain over past night.
Forecast 80's F next 5 days with isolated showers.

Lot 20 through 26, 3rd Street
Lot 20 front, 3rd Street
Lot 21front, 3rd Street
Lot 22 front, 3rd StreetLot 20 rear
Lot 21 rearLot 22 rearLot 23 rear Lot 1 mechanicals in progress
Lot 2 mechanicals in progress
Lot 3 mechanicals in progress
Lot 4 mechanicals in progress
Lot 5 mechanicals in progress
Lot 6 mechanicals in progress
Lot 7 mechanicals in progress

Wednesday, August 13, 2008

Project Meeting Wednesday August 13, 2008

Wednesday August 13, 2008
Mid 80's F clear, 60's F overnight, rain earlier in the week.
Forecast 80's and 70's for next 5 days with possibility of showers.

46% complete, payment voucher approved and signed.

Attendance;
James Thomas; Union Square Homes
Harold Thomas; Union Square Homes
Jihad Ali ; Union Square Homes
Dan Thomer; WDC Construction
Lisa Gaffney; CEDA
Michael Washington; OHCD
John Paczewski; PHFA
Colin Dawson RA; CDRA
Kevin Maguire; for TRF
Harry Ackroyd; R&V for OHCD

Distribution all in attendance and;
David Collins; AICP, OHCD

Progress;
Lot 1; Main garage roof shingles complete, rough mechanicals in progress
Lot 2; Main garage roof shingles complete, rough mechanicals in progress
Lot 3; Main garage roof shingles complete, rough mechanicals in progress
Lot 4; Main garage roof shingles complete, rough mechanicals in progress
Lot 5; Main garage roof shingles complete, rough mechanicals in progress
Lot 6: Main garage roof shingles complete, rough mechanicals in progress
Lot 7; Main garage roof shingles complete, rough mechanicals in progress

Lot 8; Main garage roof shingles complete
Lot 9; Main garage roof shingles complete
Lot 10; Main garage roof shingles complete
Lot 11; Main garage roof shingles complete
Lot 12: Main garage roof shingles complete
Lot 13; Main garage roof shingles complete

Lot 14; Main garage roof shingles complete
Lot 15; Main garage roof shingles complete
Lot 16; Main garage roof shingles complete
Lot 17; Main garage roof shingles complete
Lot 18; Main garage roof shingles complete
Lot 19; Main garage roof shingles complete

Lot 20; Siding in progress, drywall hung and finished
Lot 21; Siding in progress, drywall hung and finished
Lot 22; Siding in progress, drywall hung and finish in progress
Lot 23; Siding in progress, rough mechanicls and air sealing complete
Lot 24; Rough mechanicals and air sealing complete
Lot 25; Rough mechanicals and air sealing complete
Lot 26; Rough mechanicals and air sealing complete

Anticipated Progress next week weather permitting;
Lots 1 through7; Siding complete, rough mechanicals complete
Lot 8 through 13; Siding in progress
Lot 14 through 19: Siding in progress
Lots 20 through 26; Siding complete, drywall complete

Project schedule to be prepared by WDC upon receipt of schedule for utility work;

Exterior Sheathing
Harry Ackroyd expressed concern on prolonged exposure of wall sheathing to UV and rain; house wrap and siding will continue without interuption until complete.

DELCORA
After this meeting Colin Dawson discussed with Ambric new request from DELCORA and Catania Engineering for City Engineer: show on drawing set existing sewer in 3rd and 4th Streets and sewer backflow preventer.

PECO
PECO gas service main from 2nd Street, street work commenced.



Prepared by Colin Dawson RA

Project photographs and Field Reports available at; http://unionsquarechesterpa.blogspot.com/


Jeffery Street at 4th Street
Lots 14 through 19, Union Street
Lots 20 through 26, 3rd Street rear
PECO gas work commenced Jeffery Street 3rd to 2nd Street
Lots 20 through 26, 3rd Street
Lots 1 through 7, 4th Street

Lot 20, drywall hung and finished
Lot 21, drywall hung and finished
Lot 22, drywall hung finish in progress
Lots 22, 21 & 23 siding in progress
Lots 8 through 13, Union Street

Monday, August 4, 2008

Field Report Monday August 4, 2008

Monday August 4, 2008

Mid 80's F during day, 70's F overnight, dry.
Isolated thunder storms forecast for the next few days.
Lots 1 through 7, 4th Street
Main and garage roof shingles complete.
Mechanicals in progress.
Lots 8 through 13, Union Street
No new work.
Lots 14 through 19, Union Street
Party wall masonry complete lots 15 through 19, set up for scaffold at 14 this day.
Main and garage roof shingles complete lots 17, 18 & 19
Lots 20 through 26, 3rd Street
Drywall hung lot 20, sanitary vent through roof installed including flashing, rear patio door installation in progress.

Lots 1 through 7, 4th Street
Lots 1 through 7, 4th Street rear
Lot 14-15 masonry party wall scaffold set up
Lot 15-16 party wall
Lots 20 through 26, 3rd Street rear
Lot 20 drywall hung

Friday, August 1, 2008

Field Report Friday August 1, 2008

Friday August 1, 2008
Low 90's F during day, 70'sF overnight, no rain reported
Isolated thunderstorms forecast next few days.
Insulation installed lot 20 and 21,


Lot 1 through 7, 4th Street


Lot 1 through 7, 4th Street rear


Lot 19 roofing material on site,
Lot 18 roofing material on site, gable barge board complete,
Lot 17 gable barge board in progress
Lot 17-16 masonry party wall complete this day


Lot 17-16 party wall

Lot 20 through 26, 3rd Street rear
Lot 21 attic insulation
Lot 21 tub "P" trap fire saffing insulation
Lot 21 tub suround insulation at masonry wall inconsistent
Lot 21 tub "P" trap fire fire saffing insulation
Lot 21 2nd floor, drywall delivered
Lot 20, tub "P" trap fire saffing insulation
Lot 20, tub "P" trap fire saffing insulation, inconsistent insulation at exterior wall.

Lot 20 drywall delivered