Tuesday, November 11, 2008

Field Report Tuesday November 11, 2008

Tuesday November 1, 2008
50's F during day, 30's F overnight.
Forecast 50's and 60's with low in 40's through Saturday, and showers Thursday through Saturday.

3rd Street trench for electric and telecom in progress
Lot 7 porch slab (1 through 7 complete)
Lot 13 & 12 porch slab complete
Lot 14 insulation on site
Lot 15 insulation on site
Lot 16 insulation on siteLot 17 insulation on site
Lot 18 insulation on site
Lot 19 insulation on site





















































Friday, November 7, 2008

Field Report Friday November 7, 2008

Friday November 7, 2008
60's F dry

Lot 26 2A modified fill material for 3rd Street sidewalk area delivered.
4th Street fill compacted at new sewer

Union Street sub-paving grade. Ambric curb stake out in progress
4th Street sidewalk sub-grade

Wednesday, November 5, 2008

Field Report Wednesday November 5, 2008

Wednesday November 5, 2008
60's F scattered showers

Union Street grading
Lot 19 floor leveling
Lot 18 floor leveling
Lot 17 floor leveling
Lot 16 floor leveling

Lot 15 floor leveling

Lot 14 floor leveling

Tuesday, November 4, 2008

Field Report Tuesday November 4, 2008

Tuesday November 4, 2008

50's F scattered showers.



Porch end drop soffit in progress

4th Street and Jeffery Street curb poured

Union Street excavation to paving sub-grade in progress

Lots 1 through 7 prime paint in progress

Lots 8 through 13 rough mechanicals in progress

Lots 14 through 19 floor level compound in progress



Lot 1 porch drop soffit in progress
4th Street curb lots 1 through 7
4th Street curb, Yarnall to Jeffery
Jeffery Street curb, 4th to Union Street
Jeffery Street curb 3rd to Union
3rd Street curb at Jeffery Street
3rd Street curb at Yarnall Street
Union Street excavate to sub-paving grade progress

Monday, November 3, 2008

Field Report Monday November 3, 2008

Monday November 3, 2008
60's F, dry, forecast showers Tuesday evening through Friday

3rd Street curb poured Lots 26 through 20
4th Street curb poured lots 1 through 4
Jeffery Street curb demolition at 3rd Street through Union Street
Jeffery Street curb prep, 4th Street to Union Street