Friday, June 12, 2009

Field Report Friday June 12, 2009

Friday June 12, 2009

Today Scattered Tstms Hi 83 °F
Tonight Scattered Tstms Lo 66 °F
Saturday Chance Tstms Hi 81 °F
Saturday Night Chance Tstms Lo 62 °F
Sunday Chance Tstms Hi 80 °F
Sunday Night Chance Tstms Lo 61 °F
Monday Mostly Cloudy Hi 77 °F
Monday Night Mostly Cloudy Lo 62 °F
Tuesday Mostly Sunny Hi 80 °F

Substantial Complete inspection lots 7, 5 & 24 (no access to lot 6).
Substantial Complete Certificate and punch list available by request in comments section.

Union and Jeffery storm inlets in progress


Lot 24

Lot 5, 6 & 7.
Union and Jeffery storm inlet in progress
Union and Jeffery storm inlet

Wednesday, June 10, 2009

Project Meeting Wednesday June 10, 2009

Union Square Chester
Wednesday June 10, 2009

Today Slight Chc Tstms Hi 81 °F
Tonight Chance Tstms Lo 65 °F
Thursday Tstms Likely Hi 80 °F
Thursday Night Tstms Likely Lo 64 °F
Friday Scattered Tstms Hi 83 °F
Friday Night Scattered Showers Lo 64 °F
Saturday Mostly Sunny Hi 81 °F
Saturday Night Partly Cloudy Lo 62 °F
Sunday Partly Sunny Hi 80 °F

84% complete houses,
sitework no voucher request this meeting,

Payment voucher approved and signed

Attendance;
James Thomas; Union Square Homes
Harold Thomas; Union Square Homes
Dan Thomer; WDC Construction
Kevin Maguire; for TRF
Colin Dawson RA; CDRA
Charels Catania PE; Catania Eng/City Engineer
Lisa Gaffney; CEDA
George Troilo; OHCD

Distribution all in attendance and;
Assistant Director, Linda Hill; OHCD
Michael Washington; OHCD
Edward Koehler PE; R&V for OHCD
Joe Mulvahill; Ambric Technologies
John Paczewski; PHFA
Jihad Ali; Union Square Homes
Harry Ackroyd; R&V for OHCD

Progress;
Please note use of the term "installed" or "complete" does not include tested, inspected or approved by utility provider or public agency.

SITE

3rd Street
-Complete except fall tree planting.

Union Street
-Grading for paving subgrade in progress
-WDC projects; curbing next week, street sewer and lateral connect this month.
-City Engineer requested notification for on site review when subgrade established at crest of Union Street.

4th Street
-Sidewalk and seeding installed

Jeffery Street
-Seeded except at Union corner.
-WDC project Jeffery street sewer to commence this month.

Yarnall Street
-Sidewalk and seeding installed with exception at Union Street corners.

Trees
-WDC to discuss with landscape subcontractor availability of proposed trees, City Engineer, Ambric, CEDA and Street tree commission to review, planting will be in the Fall. Proximity to underground and overhead utilities and impact of root system on paving is off concern with City Engineer.

Mail Boxes
-USPS requested development gang box or individual box at curb line. City Engineer does not object to but does have reservation on mail box at curb line next to driveways.

Fence
-Fire Department has concern over emergency egress for homeowners, post and rail may be an option; rail slides over and drops out. WDC to review with Chester L&I and Fire Department. WDC to discuss with Chester City Planning and L&I before installation.

HOUSES

Homeowner manual
-WDC to prepare homeowner manual including maintenance item guidance.

Lot 1 through 7
-WDC punch list in progress
-Carpet installed lots 7, 6 & 5, homeowner settlement on 7 & 5 next week.

Lot 8 through 13
-Porch end gable siding installed without 15# bit felt or house wrap base, and no end gable trim board. Trim at gable showing water damage and fastener stains.
Bathroom exhaust fan vent installed in attic space without supports, vent sagging to dip over rear right bedroom closet providing an opportunity for warm moist air from bathroom condensing in vent through cold attic and pooling at low point. WDC to provide hanger straps to provide slope without dip and confirm correct support condition in all 26 units.

Lot 14 through 19
-Porch end gable siding installed without 15# bit felt or house wrap base, and no end gable trim board. Trim at gable showing water damage and fastener stains.

Lot 20 through 26
-Lots 20, 21, 22, 23, 25 26 homeowner moved in.
-Carpet installed lot 24, homeowner settlement next week.

Next project meeting 1:30 PM Wednesday July 8, 2009 to be confirmed. http://unionsquarechesterpa.blogspot.com/ for images and prior meeting and field reports.

Jeffery at 4th
4th at Jeffery
Union at Jeffery southside
Union at Jeffery northside
Jeffery at 3rd
3rd at Jeffery
4th and Union rear at Yarnall
4th Street touch up paint

Tuesday, June 2, 2009

Field Report Tuesday June 2, 2009

Tuesday June 2, 2009

Today Scattered Tstms Hi 84 °F
Tonight Slight Chc Tstms Lo 65 °F
Wednesday Tstms Likely Hi 83 °F
Wednesday Night Tstms Likely Lo 61 °F
Thursday Chance Rain Hi 68 °F
Thursday Night Slight Chc Rain Lo 56 °F
Friday Partly Sunny Hi 73 °F
Friday Night Mostly Cloudy Lo 57 °F
Saturday Partly Sunny Hi 77 °F

Lot 7, 5 & 24 carpet installed, WDC punch list in progress.

4th Street, sidewalk and driveway paving complete, street paving restore in progress
4th and Union rear grading and seeding in progress, straw cover.
Yarnall Street, 4th to Union, seeded and straw cover, street paving restore in progress
Jeffery Street, 4th to Union sidewalk paving complete, seeded and straw cover.

3rd Street
4th and Union rear
4th Street, street paving restore
4th Street, street paving restore
Yarnall Street, 4th to Union street paving restore in progress
3rd and Union rear, green.
Yarnall Street, 3th to Union, seeded and straw cover

Tuesday, May 26, 2009

Field Report Tuesday May 26, 2009

Tuesday May 26, 2009

Today Rain Hi 61 °F
Tonight Rain Likely Lo 55 °F
Wednesday Chance Tstms Hi 76 °F
Wednesday Night Chance Tstms Lo 62 °F
Thursday Chance Tstms Hi 78 °F
Thursday Night Chance Tstms Lo 66 °F
Friday Chance Tstms Hi 81 °F
Friday Night Partly Cloudy Lo 59 °F
Saturday Sunny Hi 77 °F

Lot 7 & 6 finish plumbing and electric installed.
Lot 5, 4 & 3 finish plumbing and electric in progress.

AC condenser installed lots 1 through 7
Rear concrete pads installed lot 1 through 7
Rear concrete pads formed lots 8 through 13 (no mechanical tie evident to house foundation wall)
4th Street sidewalk concrete installed lots 7, 6 & 5, formed for 4, 3, 2 & 1
4th Street meter protection bollards, tube forms placed.
4th Street and Yarnall Street, concrete base for roadway restore at curb in progress.


4th Street concrete sidewalk lot 7 through 5

4th Street sidewalk stone base and formwork, lots 1 through 4
4th and Jeffery roadway concrete base restore at curb
Jeffery Street sidewalk stone base Union to 4th
Union Street northside rear, formed for concrete pads
4th Street rear, concrete pads and AC condenser

Wednesday, May 20, 2009

Field Report Wednesday May 20, 2009

Wednesday May 20, 2009

Today-Sunny Hi 79 °F
Tonight-Clear Lo 54 °F
Thursday-Sunny Hi 82 °F
Thursday Night-Mostly Clear Lo 59 °F
Friday-Sunny Hi 83 °F
Friday Night-Partly Cloudy Lo 61 °F
Saturday-Partly Sunny Hi 78 °F
Saturday Night-Chance Tstms Lo 60 °F
Sunday-Mostly Cloudy Hi 77 °F

Yarnall Street sidewalk pored 3rd to Union and 4th to Union, including 3rd and Union corner

3rd and Jeffery sidewalk corner poured.

4th Street stone base for sidewalk in progress.

Lot 1 through 7 kitchen cabinets and countertop installed

Lot 6 & 7 finish plumbing and paint touch-up in progress

Jeffery Street sidewalk grading, 4th to Union in progress.
4th Street lots 1 through 7
Union Street from Jeffery Street
3rd and Union rear
3rd Street lots 20 through 26
4th and Union rear from Jeffery
Jeffery sidewalk grading 4th to Union
Lot 7 1st floor bathroom
Lot 7 kitchen
Lot 7 2nd floor hall bathroom
Lot 7 paint touch-up in progress
Lot 7 through 1, 4th Street
Yarnall Street sidewalk, 4th to Union
Yarnall and 4th corner curb pour
Yarnall sidewalk, Union to 4th
Yarnall sidewalk, 3rd to Union
Yarnall and 3rd corner sidewalk
3rd and Jeffery, corner sidewalk