Friday, August 28, 2009

Field Report Friday August 28, 2009

Friday August 28, 2009

This Afternoon Heavy Rain Hi 78 °F
Tonight Heavy Rain Lo 69 °F
Saturday Showers Likely Hi 84 °F
Saturday Night Chance Tstms Lo 69 °F
Sunday Chance Tstms Hi 83 °F
Sunday Night Slight Chc Tstms Lo 63 °F
Monday Partly Sunny Hi 77 °F
Monday Night Partly CloudyLo 60 °F
Tuesday Mostly Sunny Hi 75 °F

Union Street asphalt paving binder course installed
CWA on site installing water meters.

Union Street

Wednesday, August 26, 2009

Project Meeting Wednesday August 26, 2009

Project Meeting Wednesday August 26, 2009

Today Sunny Hi 89 °F
Tonight Mostly Cloudy Lo 68 °F
Thursday Partly Sunny Hi 84 °F
Thursday Night Chance Showers Lo 66 °F
Friday Chance Tstms Hi 79 °F
Friday Night Chance Tstms Lo 67 °F
Saturday Chance Tstms Hi 79 °F
Saturday Night Chance Tstms Lo 68 °F
Sunday Chance Tstms Hi 82 °F

94% complete houses,
92% complete infrastructure / sitework

Payment vouchers approved and signed

Attendance;
James Thomas; Union Square Homes
Harold Thomas; Union Square Homes
Dan Thomer; WDC Construction
Kevin Maguire; for TRF
Colin Dawson RA; CDRA
Jihad Ali; Union Square Homes
Harry Ackroyd; R&V for OHCD
Charles Catania PE; Catania Eng/City Engineer
Lisa Gaffney; CEDA
George Troilo; OHCD

Distribution all in attendance and;
John Paczewski; PHFA
Assistant Director, Linda Hill; OHCD
Michael Washington; OHCD
Edward Koehler PE; R&V for OHCD
Joe Mulvahill; Ambric Technologies

Progress;Please note use of the term "installed" or "complete" does not include tested, inspected or approved by utility provider or public agency.

SITE

3rd Street
-Substantially complete

4th Street
-Substantially complete

Yarnall Street
-Curbs and sidewalk installed
-Storm inlets installed, Union northside vand Yarnall cold patch, Union southside and Yarnall steelplate.

Jeffery Street
-Sanitary sewer complete
Curbs and sidewalk installed

Union Street
-Slip form curb installed, sidewalks and driveways installed
-Curb inlets installed
-Sanitary sewer installed and house laterals
-CWA main installed and laterals to meter pits
-Infrasource gas, electric, telecom installed to meter locations
-Road grade stone base in progress

Trees;
-WDC reports tree planting after September 15, 2009

Mail Boxes;
-Not yet resolved

Fence;
-Union Square Homes reports agreement with homeowners association in progress for fence installation.

Houses;

Lot 1 through 7
-Substantial complete lots

Lot 8 through 13
-Finish electric complete
-Finish HVAC complete (condensers installed closer to homeowner move in
-Finish plumbing in progress
-Kitchen cabinets, counter and flooring complete
-Bathrooms complete including tile

Lot 14 through 19
-WDC punch list prior to carpet in progress

Lot 20 through 26
-Substantial complete

This is the final project meeting, progress report will be issued until all houses and site work is substantially complete. WDC anticipates substantial complete by end of September 2009.

http://unionsquarechesterpa.blogspot.com/ for images and prior meeting and field reports.



Union Street subgrade stone base in progress, binder asphalt paving Thursday August 27, 2009.

Monday, August 24, 2009

Field Report Monday August 24, 2009

Monday August 24, 2009

This Afternoon Isolated Tstms Hi 87 °F
Tonight Mostly Clear Lo 67 °F
Tuesday Sunny Hi 89 °F
Tuesday Night Mostly Clear Lo 71 °F
Wednesday Sunny Hi 92 °F
Wednesday Night Slight Chc Showers Lo 71 °F
Thursday Partly Sunny Hi 83 °F
Thursday Night Mostly CloudyLo 66 °F
Friday Chance Tstms Hi 81 °F

Union Street subgrade prep in progress

Thursday, August 20, 2009

Field Report Thursday August 20, 2009

Thursday August 16, 2009

This Afternoon Heavy Rain Hi 90 °F
Tonight Heavy Rain Lo 73 °F
Friday Chance Tstms Hi 90 °F
Friday Night Tstms Likely Lo 73 °F
Saturday Tstms Likely Hi 86 °F
Saturday Night Chance Tstms Lo 68 °F
Sunday Mostly Sunny Hi 85 °F
Sunday Night Partly Cloudy Lo 65 °F
Monday Mostly Sunny Hi 82 °F

Union Street both sides seeded and straw cover
Tyson layout Union road grade reference stakes in progress
Union southside and Yarnall curb inlet connect to Yarnall combined sewer in progress.
C&C repair Union Street porch concrete cracks in progress

Union northside and Yarnall
Union Street Tyson reference stakes
Union and Yarnall curb inlet connection, concrete encasement at existing brick sewer
Union and Yarnall inlet connection
Union and Yarnall PA 3B fill delivered
Union and Yarnall inlet fill compaction
Union and Yarnall fill lift

Tuesday, August 18, 2009

Field Report Tuesday August 18, 2009

Tuesday August 18, 2009

Today Slight Chc Tstms Hi 92 °F
Tonight Chance Tstms Lo 74 °F
Wednesday Chance Tstms Hi 90 °F
Wednesday Night Chance Tstms Lo 73 °F
Thursday Chance Tstms Hi 88 °F
Thursday Night Chance Tstms Lo 74 °F
Friday Chance Tstms Hi 88 °F
Friday Night Chance Tstms Lo 73 °F
Saturday ChanceTstmsHi 84 °F

CWA completed water service laterals and meter pits.
Union southside and Yarnall curb inlet connect in progress.
Union north and southside top soil and grading for seeding in progress.
Union northside kitchen cabinets installed, vinyl flooring in progress
Union southside, finish electric and finish plumbing in progress.

CWA water service lateral
Union northside top soil in progress
Union CWA on site
Lot 13 kitchen
Lot 12 kitchen
Lot 11 kitchen
Lot 10 kitchen
Lot 9 kitchen
Lot 8 kitchen
Union northside
Union southside
Lot 14 kitchen
Lot 15 kitchen
Lot 16 kitchen
Lot 17 kitchen
Lot 18 kitchen
Lot 19 kitchen
Union southside and Yarnall curb inlet