Wednesday, March 4, 2009

Field Report Wednesday March 4, 2009

Wednesday March 4, 2009

Today Sunny Hi 33°F
Tonight Mostly Clear Lo 20°F
Thursday Mostly Sunny Hi 42°F
Thursday Night Slight Chc Showers Lo 33°F
Friday Slight Chc Showers Hi 52°F
Friday Night Mostly Cloudy Lo 41°F
Saturday Partly Sunny Hi 62°F
Saturday Night Mostly Cloudy Lo 41°F
Sunday Partly Sunny Hi 58°F

Union Street sanitary laterals to curb in progress.

4th Street at Jeffery
Union Street at Jeffery
Jeffery Street at 3rd
3rd Street at Jeffery
Typical sanitary lateral (lots 8 through 13 installed, 14 through 19 in progress)
Lot 13

Thursday, February 26, 2009

Field Report Thursday February 26, 2009

Thursday February 26, 2009


Today Partly Sunny Hi 50°F
Tonight Mostly Cloudy Lo 38°F
Friday Showers Likely Hi 58°F
Friday Night Showers Likely Lo 34°F
Saturday Slight Chc Showers Hi 45°F
Saturday Night Snow/Sleet Lo 31°F
Sunday Chance Rain/Snow Hi 41°F
Sunday Night Chance Snow Lo 25°F
Monday Partly Sunny Hi 36°F

3rd Street paving and driveway base in progress; approximatly 20" saturated soils removed, 2A modified fill installed in two 8" lifts and compacted, stone dust for sub-paving slab base.

4th and Union infiltration basin manhole set.



3rd Street and Yarnall Street
Union Street at Yarnall Street
Yarnall Street at 4th Street
4th Street at Yarnall Street
Union and 4th infiltration basin manhole set

Union and 4th manhole cone set
3rd Street driveway rammex compaction
3rd Street driveway paving base in progress
3rd Street paving geofabric base

Tuesday, February 24, 2009

Field report Tuesday February 24, 2009

Tuesday February 24, 2009

Tonight Mostly Clear Lo 19°F
Wednesday Sunny Hi 44°F
Wednesday Night Partly Cloudy Lo 31°F
Thursday Slight Chc Rain Hi 53°F
Thursday Night Chance Rain Lo 43°F
Friday Rain Likely Hi 53°F
Friday Night Chance Showers Lo 29°F
Saturday Sunny Hi 43°F
Saturday Night Mostly Clear Lo 29°F

3rd Street, prep for driveways in progress

Yarnall Street curbs removed.

PECO Gas Jeffery Street permanent concrete base for street paving complete.


3rd Street, driveway prep
Jeffery Street PECO gas street restore
4th Street new PECO pole on site
Yarnall Street Union to 4th curb removed
Yarnall Street 3rd to Union removed
3rd and Jeffery PECO gas street restore

Friday, February 20, 2009

Friday February 20, 2009

Friday February 20, 2009

This Afternoon Breezy Hi 36°F
Tonight Mostly Clear Lo 22°F
Saturday Mostly Sunny Hi 40°F
Saturday Night Chance Rain/Snow Lo 27°F
Sunday Chance Rain/Snow Hi 40°F
Sunday Night Mostly Cloudy Lo 25°F
Monday Sunny Hi 38°F
Monday Night Mostly Clear Lo 23°F
Tuesday Mostly Sunny Hi 40°F

4th and Union Infiltration basin storm laterals in progress

3rd and Union infiltration basin, Jeffery manhole in progress, concrete storm pipe run from basin manhole to 3rd Street manhole.

3rd and Jeffery manhole installed and street patched.

PECO Gas on site Jeffery between 3rd and 2nd, trench sawcut to new gas service valve at Jeffery and Union.

Lot 10, 11, 12 storm laterals
Lot 10 storm lateral
Lot 11 storm lateral
Lot 12 storm lateral
3rd and Jeffery manhole street patch
3rdand Jeffery existing manhole with storm connection
3rd and Union infiltration basin manhole installation

Monday, February 16, 2009

Field Report Monday February 16, 2009

Monday February 16, 2009

Tonight Mostly Clear Lo 24°F
Tuesday Sunny Hi 43°F
Tuesday Night Partly Cloudy Lo 27°F
Wednesday Rain/Snow Hi 42°F
Wednesday Night Rain Lo 37°F
Thursday Chance Showers Hi 47°F
Thursday Night Mostly Cloudy Lo 26°F
Friday Mostly Sunny Hi 40°F
Friday Night Partly Cloudy Lo 25°F

New Verizon pole installed, to be compacted and additional brace added
Precast manhole modified for use at existing brick sewer in Jeffery Street
4th and Union infiltration basin, Jeffery Street end.