Field Report Monday May 4, 2009

Monday May 4, 2009

Today Rain Hi 57 °F
Tonight Rain Lo 51 °F
Tuesday Chance Rain Hi 61 °F
Tuesday Night Slight Chc Showers Lo 52 °F
Wednesday Slight Chc Showers Hi 71 °F
Wednesday Night Chance Tstms Lo 61 °F
Thursday Chance Tstms Hi 76 °F
Thursday Night Chance Tstms Lo 59 °F
Friday Partly Sunny Hi 74 °F

Lot 24 & 25 moved in.

3rd and Jeffery corner curb installed.
Jeffery sidewalk 3rd to Union in progress.
3rd and Yarnall curb inlet box and corner curb restored.
Yarnall curb, 3rd to Union and Union to 4th installed.

PECO electric conduit run to all Union and 4th junction locations, including;
- transformer at Union northside and Yarnall
- trench run from Union and Yarnall to junction box at 4th and Yarnall
- junction boxes on 4th Street

PECO gas conduit run to lots 1 & 2 (previously to Union Street)

Progress this week will be delayed due to extended periods of rain.

3rd and Jeffery corner curb
Jeffery sidewalk 3rd to Union
3rd and Yarnall corner curb and inlet
Yarnall Street curb, 3rd to Union
Yarnall curb 4th to Union and PECO electric junction box and infrasource trench
4th Street infrasource trench
4th Street typical PECO electric junction box

4th Street PECO gas typical conduit, and electric service conduit

Wednesday, April 29, 2009

Field Report Wednesday April 29, 2009

Wednesday April 29, 2009

Today Showers Likely Hi 61 °F
Tonight Mostly Cloudy Lo 42 °F
Thursday Slight Chc Showers Hi 64 °F
Thursday Night Chance Showers Lo 53 °F
Friday Chance Tstms Hi 79 °F
Friday Night Showers Likely Lo 58 °F
Saturday Tstms Likely Hi 76 °F
Saturday Night Chance Tstms Lo 54 °F
Sunday Chance Showers Hi 70 °F

Official opening by City of Chester Mayor Butler

New homeowners moves-in lots 20, 21, 22 & 23

Mayor Butler
3rd Street

Tuesday, April 28, 2009

Field Report Tuesday April 28, 2009

Tuesday April 28, 2009

Today Sunny Hi 90 °F
Tonight Tstms Likely Lo 58 °F
Wednesday Showers Likely Hi 62 °F
Wednesday Night Chance Rain Lo 50 °F
Thursday Chance Rain Hi 62 °F
Thursday Night Rain Likely Lo 54 °F
Friday Chance Tstms Hi 78 °F
Friday Night Chance Showers Lo 58 °F
Saturday Tstms Likely Hi 77 °F

3rd Street lots 25 & 26 substantially complete, punch list available by request in comment section.


3rd Street, CWA contractor final street paving repair

3rd Street, CWA contractor street paving final repair
4th Street lot 6 infrasource utility trench in progress
4th Street typical infrasource trench, 1 through 5 excavated, 6 in progress.
Jeffery and Union Verizon pole activation in progress.
Jeffery Street, 3rd to Union formed for sidewalk pour including corner.

Monday, April 27, 2009

Field Report Monday April 27, 2009

Monday April 27, 2009

3rd day above 90 deg F, heatwave.

Today Sunny Hi 92 °F
Tonight Clear Lo 65 °F
Tuesday Sunny Hi 88 °F
Tuesday Night Chance Tstms Lo 60 °F
Wednesday Chance Showers Hi 68 °F
Wednesday Night Slight Chc Showers Lo 50 °F
Thursday Partly Sunny Hi 63 °F
Thursday Night Chance Tstms Lo 53 °F
Friday Chance Tstms Hi 72 °F

Substantial complete lot 22 & 23 this day, substantial complete punch list by request in comment section.



3rd Street storm doors, extra to contract, in progress.

3rd Street lots 23 through 26
Jeffery Street sidewalk, 3rd to Union, prep in progress
Union and Yarnall transformer set, not energized.
Yarnall Street curb, Union to 4th, saturated base removed and recompacted.
Yarnall Street curb, 3rd to Union, saturated base removed and recompacted.
3rd and Union rear yard top soil installed.
4th and Jeffery, compacted fill in progress sanitary sewer to intersection manhole.

Tuesday, April 21, 2009

Field Report Tuesday April 21, 2009

Tuesday April 21, 2009

Today Chance Tstms Hi 68 °F
Tonight Chance Tstms Lo 48 °F
Wednesday Scattered Tstms Hi 60 °F
Wednesday Night Isolated Tstms Lo 40 °F
Thursday Breezy Hi 61 °F
Thursday Night Mostly Clear Lo 43 °F
Friday Sunny Hi 71 °F
Friday Night Partly Cloudy Lo 54 °F
Saturday Mostly Sunny Hi 82 °F

Substantial Complete Punch List Inspection for lots 20 and 21 this day, punch list by request in comments section.



Union Street infrasource utilities in progress.
Union Street northside
Union Street northside utility junction box
Union Street northside and Yarnall Street infrasource utility, main junction excavation.
Yarnall Street sidewalk prep., 3rd to Union
3rd Street curbside street paving restoration.