Wednesday, March 11, 2009

Project Meeting Wednesday March 11, 2009

Project Meeting Wednesday March 11, 2009


Today Slight Chc Rain Hi 62 °F
Tonight Partly Cloudy Lo 33 °F
Thursday Sunny Hi 46 °F
Thursday Night Mostly Clear Lo 28 °F
Friday Sunny Hi 44 °F
Friday Night Partly Cloudy Lo 34 °F
Saturday Mostly Sunny Hi 49 °F
Saturday Night Partly Cloudy Lo 36 °F
Sunday Mostly Sunny Hi 52 °F

72% complete,
payment voucher approved and signed

Attendance;
James Thomas; Union Square Homes
Harold Thomas; Union Square Homes
Jihad Ali ; Union Square Homes
Dan Thomer; WDC Construction
Kevin Maguire; for TRF
Colin Dawson RA; CDRA
John Paczewski; PHFA
Lisa Gaffney; CEDA
Harry Ackroyd; R&V for OHCD
Edward Koehler PE; R&V for OHCD
Troilo G; OHCD

Distribution all in attendance and;
Assistant Director, Linda Hill; OHCD
Michael Washington; OHCD

Progress;
Please note use of the term "installed" does not include tested, inspected or approved by utility provider or public agency.

3rd Street
Sidewalk and driveway graded for paving, sub-paving stone in progress
Site utilities complete and energized, with exception of Verizon Vios final run to service connection at Union and Jeffery.

3rd and Union Infiltration Basin
Infiltration Basin installed including house storm laterals, Yarnall clean-out, Jeffery manhole, and 15" concrete storm sewer to existing manhole in 3rd Street.

Union Street
House sanitary sewer laterals to cart-way installation in progress. Ambric/DELCORA/City Engineer in review of proposal to relocate proposed sewer location to avoid conflict with PECO conduit at Union and Jeffery.



4th and Union Infiltration Basin
Infiltration Basin installed including; Yarnall clean-out, Jeffery manhole, and house storm sewer laterals in progress. 15" concrete storm sewer to be run to 3rd and Union infiltration basin manhole upon preliminary resolution of PECO conduit conflict at Union and Jeffery.

4th Street
Sanitary sewer installed to existing manhole in 4th and Jeffery.
CWA water service to each lot installed

Jeffery Street
3rd Street house sanitary sewers installed to new manhole on existing Jeffery Street brick sewer.
Verizion Vios utility pole relocated, additional brace to be added after sidewalk installed.

Yarnall Street
Curbing removed, roadway sawcut for new curb installation

Lot 1 through 7
Porch finish work in progress
Finish electric in progress
Lot 8 through 13
Close-in inspection in progress
Porch finish work in progress
Lot 14 through 19
Prime painted and finish paint in progress
Porch finish work in progress
Lot 20 through 26
Utilities energized with exception of Verizon Vios.

Next project meeting 1st, or 2nd Wednesday of April, to be confirmed.

http://unionsquarechesterpa.blogspot.com/ for images and prior meeting and field reports.



3rd Street paving stone base
3rd Street at Yarnall Street
3rd and Union rear
Union Street at Yarnall Street
4th and Union rear
4th Street at Yarnall Street
Union Street typical sanitary sewer lateral
4th and Union infiltration basin typical storm sewer lateral
Yarnall Street Union to 4th sawcut for curb work
Yarnall Street Union to 3rd, sawcut for curb work