Project
Meeting Wednesday April 8, 2009
Today Slight
Chc Sprinkles Hi 53 °F
Tonight Mostly Cloudy Lo 39 °F
Thursday Mostly Sunny Hi 63 °F
Thursday Night Partly Cloudy Lo 44 °F
Friday Chance Rain Hi 57 °F
Friday Night Rain Likely Lo 45 °F
Saturday Chance Rain Hi 54 °F
Saturday Night Mostly Cloudy Lo 36 °F
Sunday Sunny Hi 55 °F
75% complete houses,
76% complete
sitework,
Payment voucher approved and signed
Attendance;James Thomas; Union Square Homes
Harold Thomas; Union Square Homes
Dan
Thomer;
WDC Construction
Kevin
Maguire; for
TRFColin Dawson RA;
CDRAJohn
Paczewski;
PHFALisa
Gaffney;
CEDAHarry
Ackroyd; R&V for
OHCDGeorge
Troilo;
OHCDDistribution all in attendance and;
Assistant Director, Linda Hill;
OHCDMichael Washington;
OHCDEdward
Koehler PE; R&V for
OHCDJihad Ali ; Union Square Homes
Progress;Please note use of the term "installed" does not include tested, inspected or approved by utility provider or public agency.
3rd StreetSidewalk and driveway installed
Site utilities complete and energized, with exception of Verizon
Vios final run to service connection at Union and Jeffery.
Trench for
infrasource and Verizon conduit Union Street north side and
Yarnall Street in progress.
Front yard sod in progress.
Union StreetHouse sanitary sewer laterals to proposed Union Street sewer main location installed.
Ambric/
DELCORA/City Engineer in review of proposal to relocate proposed sewer location to avoid conflict with
PECO conduit at Union and Jeffery.
Trenching for
PECO gas and electric conduit, Verizon conduit and
Comcast conduit in progress, including sections of conduit.
4th and Union Infiltration BasinInfiltration Basin installed including; house storm sewer laterals and 15" concrete storm sewer to 3rd and Union infiltration basin manhole.
Yarnall StreetCurbing removed, roadway
sawcut for new curb installation
Trees WDC to provide
CEDA with tree selection from previously presented list, and schedule for planting including locations.
Homeowner manualWDC to prepare homeowner manual including
maintenance item guidance.
Lot 1 through 7Porch finish work and siding in progress, (no end gable trim board).
Finish electric installed (not energized)
Lot 8 through 13Porch end gable siding installed without 15# bit felt or house wrap base, (no end gable trim board)
Lot 14 through 19Porch end gable siding installed without 15# bit felt or house wrap base, (no end gable trim board)
Rear concrete pads in progress garage and patio doors, (no mechanical tie to house foundation wall, soil may not be fully compacted)
Lot 20 through 26Utilities energized with exception of Verizon
Vios.
Carpet installed.
WDC punch list work in progress
Rear concrete pads in progress garage and patio doors, (no mechanical tie to house foundation wall, soil may not be fully compacted)
Next project meeting 1:30 PM Wednesday May 13, 2009 to be confirmed.
http://unionsquarechesterpa.blogspot.com/ for images and prior meeting and field reports.

3rd Street sod in progress

3rd Street top soil for sod

Yarnall Street infrasource trench in progress

Union Street utility conduit in progress

Union Street southside rear concrete pad prep and form

3rd Street rear concrete pad pour