Wednesday, April 8, 2009

Project Meeting Wednesday April 8, 2009

Project Meeting Wednesday April 8, 2009

Today Slight Chc Sprinkles Hi 53 °F
Tonight Mostly Cloudy Lo 39 °F
Thursday Mostly Sunny Hi 63 °F
Thursday Night Partly Cloudy Lo 44 °F
Friday Chance Rain Hi 57 °F
Friday Night Rain Likely Lo 45 °F
Saturday Chance Rain Hi 54 °F
Saturday Night Mostly Cloudy Lo 36 °F
Sunday Sunny Hi 55 °F

75% complete houses,
76% complete sitework,

Payment voucher approved and signed

Attendance;
James Thomas; Union Square Homes
Harold Thomas; Union Square Homes
Dan Thomer; WDC Construction
Kevin Maguire; for TRF
Colin Dawson RA; CDRA
John Paczewski; PHFA
Lisa Gaffney; CEDA
Harry Ackroyd; R&V for OHCD
George Troilo; OHCD

Distribution all in attendance and;
Assistant Director, Linda Hill; OHCD
Michael Washington; OHCD
Edward Koehler PE; R&V for OHCD
Jihad Ali ; Union Square Homes

Progress;
Please note use of the term "installed" does not include tested, inspected or approved by utility provider or public agency.

3rd Street
Sidewalk and driveway installed
Site utilities complete and energized, with exception of Verizon Vios final run to service connection at Union and Jeffery.
Trench for infrasource and Verizon conduit Union Street north side and Yarnall Street in progress.
Front yard sod in progress.

Union Street
House sanitary sewer laterals to proposed Union Street sewer main location installed.
Ambric/DELCORA/City Engineer in review of proposal to relocate proposed sewer location to avoid conflict with PECO conduit at Union and Jeffery.
Trenching for PECO gas and electric conduit, Verizon conduit and Comcast conduit in progress, including sections of conduit.

4th and Union Infiltration Basin
Infiltration Basin installed including; house storm sewer laterals and 15" concrete storm sewer to 3rd and Union infiltration basin manhole.

Yarnall Street
Curbing removed, roadway sawcut for new curb installation

Trees
WDC to provide CEDA with tree selection from previously presented list, and schedule for planting including locations.

Homeowner manual
WDC to prepare homeowner manual including maintenance item guidance.

Lot 1 through 7
Porch finish work and siding in progress, (no end gable trim board).
Finish electric installed (not energized)

Lot 8 through 13
Porch end gable siding installed without 15# bit felt or house wrap base, (no end gable trim board)

Lot 14 through 19
Porch end gable siding installed without 15# bit felt or house wrap base, (no end gable trim board)
Rear concrete pads in progress garage and patio doors, (no mechanical tie to house foundation wall, soil may not be fully compacted)

Lot 20 through 26
Utilities energized with exception of Verizon Vios.
Carpet installed.
WDC punch list work in progress
Rear concrete pads in progress garage and patio doors, (no mechanical tie to house foundation wall, soil may not be fully compacted)

Next project meeting 1:30 PM Wednesday May 13, 2009 to be confirmed.
http://unionsquarechesterpa.blogspot.com/ for images and prior meeting and field reports.


3rd Street sod in progress
3rd Street top soil for sod
Yarnall Street infrasource trench in progress
Union Street utility conduit in progress
Union Street southside rear concrete pad prep and form
3rd Street rear concrete pad pour