Wednesday, August 26, 2009

Project Meeting Wednesday August 26, 2009

Project Meeting Wednesday August 26, 2009

Today Sunny Hi 89 °F
Tonight Mostly Cloudy Lo 68 °F
Thursday Partly Sunny Hi 84 °F
Thursday Night Chance Showers Lo 66 °F
Friday Chance Tstms Hi 79 °F
Friday Night Chance Tstms Lo 67 °F
Saturday Chance Tstms Hi 79 °F
Saturday Night Chance Tstms Lo 68 °F
Sunday Chance Tstms Hi 82 °F

94% complete houses,
92% complete infrastructure / sitework

Payment vouchers approved and signed

Attendance;
James Thomas; Union Square Homes
Harold Thomas; Union Square Homes
Dan Thomer; WDC Construction
Kevin Maguire; for TRF
Colin Dawson RA; CDRA
Jihad Ali; Union Square Homes
Harry Ackroyd; R&V for OHCD
Charles Catania PE; Catania Eng/City Engineer
Lisa Gaffney; CEDA
George Troilo; OHCD

Distribution all in attendance and;
John Paczewski; PHFA
Assistant Director, Linda Hill; OHCD
Michael Washington; OHCD
Edward Koehler PE; R&V for OHCD
Joe Mulvahill; Ambric Technologies

Progress;Please note use of the term "installed" or "complete" does not include tested, inspected or approved by utility provider or public agency.

SITE

3rd Street
-Substantially complete

4th Street
-Substantially complete

Yarnall Street
-Curbs and sidewalk installed
-Storm inlets installed, Union northside vand Yarnall cold patch, Union southside and Yarnall steelplate.

Jeffery Street
-Sanitary sewer complete
Curbs and sidewalk installed

Union Street
-Slip form curb installed, sidewalks and driveways installed
-Curb inlets installed
-Sanitary sewer installed and house laterals
-CWA main installed and laterals to meter pits
-Infrasource gas, electric, telecom installed to meter locations
-Road grade stone base in progress

Trees;
-WDC reports tree planting after September 15, 2009

Mail Boxes;
-Not yet resolved

Fence;
-Union Square Homes reports agreement with homeowners association in progress for fence installation.

Houses;

Lot 1 through 7
-Substantial complete lots

Lot 8 through 13
-Finish electric complete
-Finish HVAC complete (condensers installed closer to homeowner move in
-Finish plumbing in progress
-Kitchen cabinets, counter and flooring complete
-Bathrooms complete including tile

Lot 14 through 19
-WDC punch list prior to carpet in progress

Lot 20 through 26
-Substantial complete

This is the final project meeting, progress report will be issued until all houses and site work is substantially complete. WDC anticipates substantial complete by end of September 2009.

http://unionsquarechesterpa.blogspot.com/ for images and prior meeting and field reports.



Union Street subgrade stone base in progress, binder asphalt paving Thursday August 27, 2009.

No comments: