Thursday, March 26, 2009

Field Report Thursday March 26, 2009

Thursday March 26, 2009

This Afternoon Rain Hi 50 °F
Tonight Rain Likely Lo 43 °F
Friday Mostly Sunny Hi 64 °F
Friday Night Chance Rain Lo 44 °F
Saturday Chance Rain Hi 56 °F
Saturday Night Tstms LikelyLo 46 °F
Sunday Showers Likely Hi 62 °F
Sunday Night Mostly Cloudy Lo 39 °F
Monday Mostly Sunny Hi 60 °F

4th and Union;
storm sewer laterals to infiltration basin installed except lot 1

Union Street north side lots 8 through 13;
infrasource trench in progress,
sanitary sewer north side main trench in progress.

3rd Street;
concrete sidewalk and driveway installed except porch to corner at Jeffery and Yarnall,
carpet in progress,
garage doors in progress,

Yarnall Street;
base material placed for curbing.

4th Street at Yarnall
Yarnall Street at 4th
Yarnall Street at 3rd
3rd Street at Yarnall
3rd Street at Jeffery
Jeffery Street at 3rd
Union Street at Jeffery
Jeffery Street at 4th
4th Street at Jeffery
3rd Street garage door typical
3rd Street living room carpet typical
3rd and Union rear
4th and Union rear
3rd Street sidewalk
Yarnall Street curb prep, Union to 3rd
Yarnall Street curb prep, Union to 4th
Union Street north side infrasource trench
Union Street north side sanitary sewer trench

Saturday, March 21, 2009

Field Report Sarurday March 21, 2009

Saturday March 21, 2009

This Afternoon Sunny Hi 51 °F
Tonight Partly Cloudy Lo 35 °F
Sunday Mostly Sunny Hi 59 °F
Sunday Night Partly Cloudy Lo 34 °F
Monday Sunny Hi 48 °F
Monday Night Mostly Clear Lo 32 °F
Tuesday Sunny Hi 50 °F
Tuesday Night Partly Cloudy Lo 37 °F
Wednesday Mostly Sunny Hi 54 °F

3rd Street sidewalk in progress, insulation blanket.

Yarnell Street excavation for in progress

Yarnell Street Union to 4th curb excavation
Yarnell and Union curb inlet
Yarnall Street 3rd to Union curb excavation
3rd Street sidewalk prep
3rd Street sidewalk pour
3rd Street sidewalk pour

Wednesday, March 18, 2009

Field Report Wednesday March 18, 2009

Wednesday March 18, 2009

This Afternoon Mostly Sunny Hi 62 °F
Tonight Slight Chc Showers Lo 44 °F
Thursday Showers Likely Hi 51 °F
Thursday Night Chance Showers Lo 33 °F
Friday Mostly Sunny Hi 47 °F
Friday Night Mostly Clear Lo 29 °F
Saturday Sunny Hi 48 °F
Saturday Night Mostly Clear Lo 30 °F
Sunday Sunny Hi 52 °F

Jeffery Street
Infiltration basin overflow storm sewer from 4th and Union manhole to Union and 3rd manhole installed.
Jeffery and Union double curb inlet installed to storm sewer overflow.

3rd Street
Stone base graded for sidewalk and driveway paving.

4th Street
PECO pole replaced

Yarnall Street
PECO replacement pole on site

Jeffery Street at 3rd Street
3rd Street at Jeffery Street
3rd and Union rear
Union Street at Jeffery Street
4th and Union rear
Jeffery Street at 4th Street
4th Street at Jeffery Street
Yarnall and Union PECO replacement pole
4th Street PECO pole replaced
Jeffery and Union double curb inlet
Jeffery Street 15" storm sewer overflow curb inlet junction box

Wednesday, March 11, 2009

Project Meeting Wednesday March 11, 2009

Project Meeting Wednesday March 11, 2009


Today Slight Chc Rain Hi 62 °F
Tonight Partly Cloudy Lo 33 °F
Thursday Sunny Hi 46 °F
Thursday Night Mostly Clear Lo 28 °F
Friday Sunny Hi 44 °F
Friday Night Partly Cloudy Lo 34 °F
Saturday Mostly Sunny Hi 49 °F
Saturday Night Partly Cloudy Lo 36 °F
Sunday Mostly Sunny Hi 52 °F

72% complete,
payment voucher approved and signed

Attendance;
James Thomas; Union Square Homes
Harold Thomas; Union Square Homes
Jihad Ali ; Union Square Homes
Dan Thomer; WDC Construction
Kevin Maguire; for TRF
Colin Dawson RA; CDRA
John Paczewski; PHFA
Lisa Gaffney; CEDA
Harry Ackroyd; R&V for OHCD
Edward Koehler PE; R&V for OHCD
Troilo G; OHCD

Distribution all in attendance and;
Assistant Director, Linda Hill; OHCD
Michael Washington; OHCD

Progress;
Please note use of the term "installed" does not include tested, inspected or approved by utility provider or public agency.

3rd Street
Sidewalk and driveway graded for paving, sub-paving stone in progress
Site utilities complete and energized, with exception of Verizon Vios final run to service connection at Union and Jeffery.

3rd and Union Infiltration Basin
Infiltration Basin installed including house storm laterals, Yarnall clean-out, Jeffery manhole, and 15" concrete storm sewer to existing manhole in 3rd Street.

Union Street
House sanitary sewer laterals to cart-way installation in progress. Ambric/DELCORA/City Engineer in review of proposal to relocate proposed sewer location to avoid conflict with PECO conduit at Union and Jeffery.



4th and Union Infiltration Basin
Infiltration Basin installed including; Yarnall clean-out, Jeffery manhole, and house storm sewer laterals in progress. 15" concrete storm sewer to be run to 3rd and Union infiltration basin manhole upon preliminary resolution of PECO conduit conflict at Union and Jeffery.

4th Street
Sanitary sewer installed to existing manhole in 4th and Jeffery.
CWA water service to each lot installed

Jeffery Street
3rd Street house sanitary sewers installed to new manhole on existing Jeffery Street brick sewer.
Verizion Vios utility pole relocated, additional brace to be added after sidewalk installed.

Yarnall Street
Curbing removed, roadway sawcut for new curb installation

Lot 1 through 7
Porch finish work in progress
Finish electric in progress
Lot 8 through 13
Close-in inspection in progress
Porch finish work in progress
Lot 14 through 19
Prime painted and finish paint in progress
Porch finish work in progress
Lot 20 through 26
Utilities energized with exception of Verizon Vios.

Next project meeting 1st, or 2nd Wednesday of April, to be confirmed.

http://unionsquarechesterpa.blogspot.com/ for images and prior meeting and field reports.



3rd Street paving stone base
3rd Street at Yarnall Street
3rd and Union rear
Union Street at Yarnall Street
4th and Union rear
4th Street at Yarnall Street
Union Street typical sanitary sewer lateral
4th and Union infiltration basin typical storm sewer lateral
Yarnall Street Union to 4th sawcut for curb work
Yarnall Street Union to 3rd, sawcut for curb work

Saturday, March 7, 2009

Field Report Saturday March 7, 2009

Saturday March 7, 2009

This Afternoon Partly Sunny Hi 67 °F
Tonight Partly Cloudy Lo 52 °F
Sunday Slight Chc Rain Hi 64 °F
Sunday Night Rain Likely Lo 45 °F
Monday Chance Rain Hi 61 °F
Monday Night Partly Cloudy Lo 38 °F
Tuesday Mostly Sunny Hi 53 °F
Tuesday Night Chance Showers Lo 36 °F
Wednesday Chance Showers

Infiltration basin end cleanouts in progress.
4th Street porch end gable siding in progress, 15# bit felt underlayment used, missing lower edge trim.

3rd and Union infiltration basin, Jeffery cleanout, 15" concrete overflow beyond
3rd and Union infiltration basin, Jeffery manhole
4th and Union infiltration basin, Jeffery cleanout, 15" concrete overflow beyond
3rd Street porch end trim and siding in progress
3rd Street porch end gable siding in progress, missing lower trim
3rd and Union infiltration basin, Yarnall cleanout in progress.
3rd Street paving base saturated.