Field Report Tuesday November 11, 2008
Tuesday November 1, 2008 50's F during day, 30's F overnight. Forecast 50's and 60's with low in 40's through Saturday, and showers Thursday through Saturday.
3rd Street trench for electric and telecom in progress Lot 7 porch slab (1 through 7 complete) Lot 13 & 12 porch slab complete Lot 14 insulation on site Lot 15 insulation on site Lot 16 insulation on siteLot 17 insulation on site