Porch end drop soffit in progress
4th Street and Jeffery Street curb poured
Union Street excavation to paving sub-grade in progress
Lots 1 through 7 prime paint in progress
Lots 8 through 13 rough mechanicals in progress
Lots 14 through 19 floor level compound in progress

Lot 1 porch drop soffit in progress

 4th Street curb lots 1 through 7

 4th Street curb, Yarnall to Jeffery

 Jeffery Street curb, 4th to Union Street

 Jeffery Street curb 3rd to Union

 3rd Street curb at Jeffery Street 
 
 3rd Street curb at Yarnall Street

 Union Street excavate to sub-paving grade progress