Construction Manager to hand deliver revised Ambric Technologies drawing set to City Engineer.
3rd Street lots 20 through 26;-Electric and gas energized
-Cut and replace section of siding at crude repair behind gas meter complete to adjacent inside corner "J".
-Drawings show approx 10" trim board at lower edge of porch roof end half gable, remove siding lower piece and install approx 10" trim board to align with top of brick veneer.
-CWA completed street blacktop repair.
Union Street lots 14 through 19;
-Downspout laterals completed to infiltration tank.
-Trim in progress.
-2nd floor bathroom plumbing repair and removal of ceiling lump at 14, 15, 16 & 17 to be completed.
Union Street lots 8 through 13;
-Miscellaneous framing items in progress including 1st floor bathroom blocking.
-Porch framing in progress.
4th Street lots 1 through 7;
-Not accessed this site visit.
Lot 23 porch end half gable
3rd and Union rear
Lot 14 downspout lateral to infiltration tank
3rd and Union rear
Lot 26 meters
Lot 25 meters
Lot 24 meters