Tuesday July 15, 2008
Low 90's F during day, high 60's overnight. Rain on Monday, forecast dry and 90's for the week.
Lot 1 through 7
Masonry party wall complete 7-6, 6-5, 5-4 and 4-3 scaffold set.
Lot 20 through 26
Rough mechanicals in progress.
Framing punch list items, also discussed with Tom Heisner L&I;
- Install exterior strap ties 1st to 2nd floor wall panels at each 3rd stud
- Install exterior strap ties 2nd floor wall panel to front gable and end gable over garage, at each 3rd stud.
- Fully nail, shim and block, wall panel to wall panel throughout, including at outside corners and garage wall to house wall.
- Install jack studs at living room/kitchen opening header.
- Install triple stud at triple joist bearing on frame walls.
- Install top hung hangers at all mutiple joist locations including triple to ledger and at stairwell, solid block as previously noted where single joist is close to triple joist and use an oversize top hung hanger.
- Through bolt built-up joist beams.
- Epoxy anchor bolt front and rear walls, 1st and 2nd floor and garage walls to masonry wall,
- Epoxy anchor main and garage roof truss to masonry wall
- Check all sill plate to masonry foundation bolts, install all nut and washer tight, install epoxy anchor bolt where anchor bolts missing including within 12" from end of each panel and not less than 48" o.c.
- Garage to house wall is a 1hr rated wall, 5/8" type "X" gwb both sides, the gwb band at ceiling framing in kitchen and laundry was installed as 1/2" gwb. Overlay or replace with 5/8" type "X" and fire tape above ceiling.
- Drywall installation must include 5/8" type "X" at garage to kitchen, laundry, 2nd floor bedroom and 2nd floor bathroom, and on garage side including over the truss adjacent to frame house wall, and 1st truss bay underside of roof sheathing.
-Lot 24; 4" sanitary stack damaged above slab, cut out and replace.
Chester L&I to be call for inspection of exterior strap ties before house wrap installed.
Tuesday, July 15, 2008
Friday, July 11, 2008
Field Report Friday July 11, 2008
Wednesday, July 9, 2008
Project Meeting Wednesday July 9, 2008
Project Meeting Wednesday July 9, 2008
This week highs 90’s and 80’s during day with thunder storms, 90’s to 70’s overnight. Showers and thunder storms forecast for next 5 days.
34% complete, payment voucher reviewed and signed.
Attendance;
James Thomas (Union Square Homes)
Lot 19; Main roof and garage roof shingles complete,
rough mechanicals in progress
Lot 20; Main roof and garage roof shingles complete,
rough mechanicals in progress
Lot 21; Main roof and garage roof shingles complete,
rough mechanicals in progress
Lot 22; Main roof and garage roof shingles complete,
rough mechanicals in progress
Lot 23; Main roof and garage roof shingles complete,
rough mechanicals in progress
Lot 24; Main roof and garage roof shingles complete,
rough mechanicals in progress
Lot 25; Main roof and garage roof shingles complete,
rough mechanicals in progress
Lot 26; Main roof and garage roof shingles complete,
rough mechanicals in progress
Anticipated Progress next week weather permitting;
Lots 1 through7; main roof sheathing complete, masonry party wall in progress
Lot 8 through 13; front gable framing and sheathing complete,
Lot 14 through 19: no new work antisipated
Lots 20 through 26; rough mechanicals complete, commence window installation
Project schedule to be prepared by WDC upon receipt of schedule for utility work;
Prepared by Colin Dawson RA
Lots 1 through 7, 4th Street at Jeffery Street
Lots 1 through 7, 4th Street rear
This week highs 90’s and 80’s during day with thunder storms, 90’s to 70’s overnight. Showers and thunder storms forecast for next 5 days.
34% complete, payment voucher reviewed and signed.
Attendance;
James Thomas (Union Square Homes)
Harold Thomas (Union Square Homes)
Jihad Ali (Union Square Homes)
Dan Thomer (WDC Construction)
Lisa Gaffney (CEDA)
Michael Washington (OHCD)
John Paczewski (PHFA)
John “King” (R&V for OHCD)
Colin Dawson RA (CDRA)
Distribution;
all in attendance and;
Kevin Maguire (for TRF)
all in attendance and;
Kevin Maguire (for TRF)
Dennis Race (Catania Eng for Chester City Engineer)
David Collins AICP, (OHCD)
David Collins AICP, (OHCD)
Harry Ackroyd (R&V for OHCD)
Progress;
Lot 1; Main roof truss and sheathing in progress
Lot 2; Main roof truss and sheathing in progress
Lot 3; Main roof truss and sheathing in progress
Lot 4; Main roof truss and sheathing in progress
Lot 5; Main roof truss and sheathing in progress
Lot 6: Main roof truss and sheathing in progress
Lot 7; Main roof truss and sheathing in progress
Lot 8; No new work this period
Lot 9; No new work this period
Lot 10; No new work this period
Lot 11; No new work this period
Lot 12: No new work this period
Lot 13; No new work this period
Lot 14; Front gable framed and sheathed
Lot 15; Front gable framed and sheathed
Lot 16; Front gable framed and sheathed
Lot 17; Front gable framed and sheathed
Lot 18; Front gable framed and sheathed
Progress;
Lot 1; Main roof truss and sheathing in progress
Lot 2; Main roof truss and sheathing in progress
Lot 3; Main roof truss and sheathing in progress
Lot 4; Main roof truss and sheathing in progress
Lot 5; Main roof truss and sheathing in progress
Lot 6: Main roof truss and sheathing in progress
Lot 7; Main roof truss and sheathing in progress
Lot 8; No new work this period
Lot 9; No new work this period
Lot 10; No new work this period
Lot 11; No new work this period
Lot 12: No new work this period
Lot 13; No new work this period
Lot 14; Front gable framed and sheathed
Lot 15; Front gable framed and sheathed
Lot 16; Front gable framed and sheathed
Lot 17; Front gable framed and sheathed
Lot 18; Front gable framed and sheathed
Lot 19; Main roof and garage roof shingles complete,
rough mechanicals in progress
Lot 20; Main roof and garage roof shingles complete,
rough mechanicals in progress
Lot 21; Main roof and garage roof shingles complete,
rough mechanicals in progress
Lot 22; Main roof and garage roof shingles complete,
rough mechanicals in progress
Lot 23; Main roof and garage roof shingles complete,
rough mechanicals in progress
Lot 24; Main roof and garage roof shingles complete,
rough mechanicals in progress
Lot 25; Main roof and garage roof shingles complete,
rough mechanicals in progress
Lot 26; Main roof and garage roof shingles complete,
rough mechanicals in progress
Anticipated Progress next week weather permitting;
Lots 1 through7; main roof sheathing complete, masonry party wall in progress
Lot 8 through 13; front gable framing and sheathing complete,
Lot 14 through 19: no new work antisipated
Lots 20 through 26; rough mechanicals complete, commence window installation
Project schedule to be prepared by WDC upon receipt of schedule for utility work;
DELCORA
Sewer agreement with DELCORA signed.
Dennis Race of Catania Engineering, (City Engineer) on site after this meeting.
CWA
Water service agreement with CWA signed this day.
PECO
PECO gas and electric service agreement signed, mechanical contractor to install electric meter blank and gas service stub, PECO installation crew to coordinate with meter locations on site.
Comfort Homes
Colin Dawson to coordinate with Comfort Homes (DoE HERS 3rd party inspection and certification) for duct testing before close-in.
Colin Dawson to coordinate with Comfort Homes (DoE HERS 3rd party inspection and certification) for duct testing before close-in.
Windows and Siding
Nail flange windows to be caulked and nailed directly to exterior sheathing, building wrap to be installed over nail flange. Dan Thomer WDC provided siding samples (previously reviewed and approved by architect), to Lisa Gafney CEDA.
Nail flange windows to be caulked and nailed directly to exterior sheathing, building wrap to be installed over nail flange. Dan Thomer WDC provided siding samples (previously reviewed and approved by architect), to Lisa Gafney CEDA.
Next Project Meeting; 1:00 PM Wednesday August 6, 2008
Prepared by Colin Dawson RA
Lots 7 through 1, 4th Street at Yarnall Street
Monday, July 7, 2008
Field Report Monday July 7, 2008
Monday July 7, 2008
High 80's and high humidity, overnight mid 70's
Frequent isolated thunderstorms over the past 4 days, and forecast for next 3 days
Lots 1 through 7
Main roof truss loaded by crane, roof truss installation in progress lots 1, 2 & 3.
Lots 8 through 13
Front gable truss loaded by crane.
Lots 14 through 19
No new work
Lots 20 through 26
Rough sanitary plumbing complete,
Rough electric, duct and "PEX" plumbing in progress.
Lots 1 through 7, 4th at Jeffery Street
High 80's and high humidity, overnight mid 70's
Frequent isolated thunderstorms over the past 4 days, and forecast for next 3 days
Lots 1 through 7
Main roof truss loaded by crane, roof truss installation in progress lots 1, 2 & 3.
Lots 8 through 13
Front gable truss loaded by crane.
Lots 14 through 19
No new work
Lots 20 through 26
Rough sanitary plumbing complete,
Rough electric, duct and "PEX" plumbing in progress.
Tuesday, July 1, 2008
Field Report Tuesday July 1, 2008
Tuesday July 1, 2008
Mid 80's F, 70's F overnight dry.
Rough Duct, Electric and Plumbing in progress lots 20 through 26
1st and 2nd floor framing complete lots 1 through 7, roof truss on site.
Lots 20 through 26, 3rd Street at JefferyStreet
Lot 22 rough, duct, electric and plumbing
Mid 80's F, 70's F overnight dry.
Rough Duct, Electric and Plumbing in progress lots 20 through 26
1st and 2nd floor framing complete lots 1 through 7, roof truss on site.
Lot 22 rough, duct, electric and plumbing