Wednesday, July 9, 2008

Project Meeting Wednesday July 9, 2008

Project Meeting Wednesday July 9, 2008

This week highs 90’s and 80’s during day with thunder storms, 90’s to 70’s overnight. Showers and thunder storms forecast for next 5 days.

34% complete, payment voucher reviewed and signed.

Attendance;
James Thomas (Union Square Homes)
Harold Thomas (Union Square Homes)
Jihad Ali (Union Square Homes)
Dan Thomer (WDC Construction)
Lisa Gaffney (CEDA)
Michael Washington (OHCD)
John Paczewski (PHFA)
John “King” (R&V for OHCD)
Colin Dawson RA (CDRA)
Distribution;
all in attendance and;
Kevin Maguire (for TRF)
Dennis Race (Catania Eng for Chester City Engineer)
David Collins AICP, (OHCD)
Harry Ackroyd (R&V for OHCD)

Progress;
Lot 1; Main roof truss and sheathing in progress
Lot 2; Main roof truss and sheathing in progress
Lot 3; Main roof truss and sheathing in progress
Lot 4; Main roof truss and sheathing in progress
Lot 5; Main roof truss and sheathing in progress
Lot 6: Main roof truss and sheathing in progress
Lot 7; Main roof truss and sheathing in progress

Lot 8; No new work this period
Lot 9; No new work this period
Lot 10; No new work this period
Lot 11; No new work this period
Lot 12: No new work this period
Lot 13; No new work this period

Lot 14; Front gable framed and sheathed
Lot 15; Front gable framed and sheathed
Lot 16; Front gable framed and sheathed
Lot 17; Front gable framed and sheathed
Lot 18; Front gable framed and sheathed

Lot 19; Main roof and garage roof shingles complete,
rough mechanicals in progress
Lot 20; Main roof and garage roof shingles complete,
rough mechanicals in progress
Lot 21; Main roof and garage roof shingles complete,
rough mechanicals in progress
Lot 22; Main roof and garage roof shingles complete,
rough mechanicals in progress
Lot 23; Main roof and garage roof shingles complete,
rough mechanicals in progress
Lot 24; Main roof and garage roof shingles complete,
rough mechanicals in progress
Lot 25; Main roof and garage roof shingles complete,
rough mechanicals in progress
Lot 26; Main roof and garage roof shingles complete,
rough mechanicals in progress

Anticipated Progress next week weather permitting;
Lots 1 through7; main roof sheathing complete, masonry party wall in progress
Lot 8 through 13; front gable framing and sheathing complete,
Lot 14 through 19: no new work antisipated
Lots 20 through 26; rough mechanicals complete, commence window installation

Project schedule to be prepared by WDC upon receipt of schedule for utility work;
DELCORA
Sewer agreement with DELCORA signed.
Dennis Race of Catania Engineering, (City Engineer) on site after this meeting.
CWA
Water service agreement with CWA signed this day.
PECO
PECO gas and electric service agreement signed, mechanical contractor to install electric meter blank and gas service stub, PECO installation crew to coordinate with meter locations on site.
Comfort Homes
Colin Dawson to coordinate with Comfort Homes (DoE HERS 3rd party inspection and certification) for duct testing before close-in.
Windows and Siding
Nail flange windows to be caulked and nailed directly to exterior sheathing, building wrap to be installed over nail flange. Dan Thomer WDC provided siding samples (previously reviewed and approved by architect), to Lisa Gafney CEDA.

Next Project Meeting; 1:00 PM Wednesday August 6, 2008

Prepared by Colin Dawson RA
Lots 7 through 1, 4th Street at Yarnall Street
Lots 1 through 7, 4th Street at Jeffery Street
Lots 1 through 7, 4th Street rear