Monday, July 21, 2008

Field Report Monday July 21, 2008

Monday July 21, 2008
Low 90's F during day, 70's F overnight, isolated thundershowers in the region but none reported in the coastal zone below the piedmont rise.

On site discussion with;
Dan Thomer: WDC
Harold Thomas: Union Square Homes
Jihad Ali: Union Square Homes
Colin Dawson: Colin Dawson RA

Masonry wall Reinforcing:
Dan prior to this meeting discussed masonry wall reinforcing with the masonry sub-contractor; placement of reinforcing has been inconsistent, and is suspect at all locations 1st floor walls, and 2nd floor lots 20 through 26 and lots 5 through 7.

Dan reports "John" his assistant observed reinforcement placement at walls lots 3 to 2, and 4 to 3, and will be onsite to observe reinforcement placement for all subsequent walls.

To provide additional lateral support for masonry walls, the epoxy anchor bolts required in the permit set to secure framing to masonry will be extended where possible and installed as through bolts with oversize galvanized fender bolts on the wall exterior.

Framing punch list lots 20 through 26:
Exterior strap ties 1st to 2nd floor panels, and gable panels in progress.
Wall panel to wall panel nailing in progress.
Wall panel sill plate bolts in progress.
Triple stud at triple joist on bearing wall (a few not done, stud may be installed at 90 deg to wall studs to clear in place electrical wire).
Top hung joist hangers at triple joist to masonry wall ledger, not done.
Top hung joist hangers at stair well double stud, not done.

5/8" type "X" drywall:
All drywall will be 5/8" type "X" for superior finish quality, the 1/2" drywall band at kitchen ceiling/garage wall will be backed-up with 5/8" drywall.
WDC requested and Colin Dawson RA approved 5/8" type "X" drywall to garage ceiling and delete drywall to garage roof void/house 2nd floor wall.

Lot 3 to 2 masonry party wall 2nd floor in progress.
Lots 8 through 13 masonry delivered.
Lot 20 exterior strap ties in place.