Tuesday, September 30, 2008

Field Report Tuesday September 30, 2008

Tuesday September 30, 2008
70's F overcast, 50's F overnight, rain at times heavy over past few days.

Water and sewer lateral installed all lots past porch/Infrasource trench location.

Sub-contractors report low supplier inventory creating problems, one piece tub/shower units have long lead times.

Lot 1 through 7;
Insulation installed lots 1, 2, 3 & 7
Drywall hung, finish in progress lots 4, 5 & 6

Lot 14 through 19;
Rough sanitary plumbing in progress.
Relocate sanitary plumbing to 2nd floor hall bathroom to match lots 1 through 7 and 20 through 26 with header at kitchen/living room passage.

Lots 20 through 26;
Kitchen and vanity installation in progress lots 20, 21 & 22
Furnace and HWH installation in progress
Finish electric and plumbing fixtures in progress.


Lot 17, plumbing to be relocated to eliminate ceiling lump.
Lot 20 kitchen
Lot 21 kitchen
Lot 22 kitchen
Lot 6 drywall
Lot 5 drywall
Lot 4 drywall
Lot 3 insulation
Lot 2 insulation
Lot 1 insulation