70's F overcast, 50's F overnight, rain at times heavy over past few days.
Water and sewer lateral installed all lots past porch/Infrasource trench location.
Sub-contractors report low supplier inventory creating problems, one piece tub/shower units have long lead times.
Lot 1 through 7;
Insulation installed lots 1, 2, 3 & 7
Drywall hung, finish in progress lots 4, 5 & 6
Lot 14 through 19;
Rough sanitary plumbing in progress.
Relocate sanitary plumbing to 2nd floor hall bathroom to match lots 1 through 7 and 20 through 26 with header at kitchen/living room passage.
Lots 20 through 26;
Kitchen and vanity installation in progress lots 20, 21 & 22
Furnace and HWH installation in progress
Finish electric and plumbing fixtures in progress.