Wednesday September 10, 2008
High 70's F dry, 60' F overnight, rain saturated ground at 3rd Street side of the site from TS Hanna on Saturday and band of heavy rain on Monday.
Forecast 70's F and 80's F for next 5 days with isolated showers.
Present;
Kevin Maguire for TRF
Harold Thomas for Union Square Homes
James Thomas for Union Square Homes
Jihad Ali for Union Square Homes
Dan Thomer for WDC
Colin Dawson RA
Payment Request Voucher signed.
Project Meeting rescheduled for Wednesday September 17, 2008 at 1:00 PM.
Due to low inventory with materials suppliers and manufacturers, some work may be partialy complete, or completed out of sequence.
Siding substantialy complete, except lot 14 front and gables in progress, and garage fronts.
Lots 1 through 7; rough mechanicals complete, air seal and fire stop complete lots 4, 5 , 6 & 7.
Lots 20 through 26; paint trim in progress, lot 20 and 21 tile in progress.
Lot 20 through 26, 3rd Street at Jeffery Street
Yarnall Street at 3rd Street
3rd Street and Union Street rear, at Yarnall Street
Union Street, south side at Yarnall Street