Lot 24 & 25 moved in.
3rd and Jeffery corner curb installed.
Jeffery sidewalk 3rd to Union in progress.
3rd and Yarnall curb inlet box and corner curb restored.
Yarnall curb, 3rd to Union and Union to 4th installed.
PECO electric conduit run to all Union and 4th junction locations, including;
- transformer at Union northside and Yarnall
- trench run from Union and Yarnall to junction box at 4th and Yarnall
- junction boxes on 4th Street
PECO gas conduit run to lots 1 & 2 (previously to Union Street)
Progress this week will be delayed due to extended periods of rain.
3rd and Jeffery corner curb
Jeffery sidewalk 3rd to Union
3rd and Yarnall corner curb and inlet
Yarnall Street curb, 3rd to Union
Yarnall curb 4th to Union and PECO electric junction box and infrasource trench
4th Street infrasource trench
HOW LONG BEFORE THE NEXT ROLL GET COMPLETED
ReplyDeleteWDC reports; saturated soils removed from Infrasource trench and clean dry fill placed and compacted the following week.
ReplyDelete