Field Report Tuesday May 26, 2009

Tuesday May 26, 2009

Today Rain Hi 61 °F
Tonight Rain Likely Lo 55 °F
Wednesday Chance Tstms Hi 76 °F
Wednesday Night Chance Tstms Lo 62 °F
Thursday Chance Tstms Hi 78 °F
Thursday Night Chance Tstms Lo 66 °F
Friday Chance Tstms Hi 81 °F
Friday Night Partly Cloudy Lo 59 °F
Saturday Sunny Hi 77 °F

Lot 7 & 6 finish plumbing and electric installed.
Lot 5, 4 & 3 finish plumbing and electric in progress.

AC condenser installed lots 1 through 7
Rear concrete pads installed lot 1 through 7
Rear concrete pads formed lots 8 through 13 (no mechanical tie evident to house foundation wall)
4th Street sidewalk concrete installed lots 7, 6 & 5, formed for 4, 3, 2 & 1
4th Street meter protection bollards, tube forms placed.
4th Street and Yarnall Street, concrete base for roadway restore at curb in progress.


4th Street concrete sidewalk lot 7 through 5

4th Street sidewalk stone base and formwork, lots 1 through 4
4th and Jeffery roadway concrete base restore at curb
Jeffery Street sidewalk stone base Union to 4th
Union Street northside rear, formed for concrete pads
4th Street rear, concrete pads and AC condenser