Field Report Friday August 1, 2008

Friday August 1, 2008
Low 90's F during day, 70'sF overnight, no rain reported
Isolated thunderstorms forecast next few days.
Insulation installed lot 20 and 21,


Lot 1 through 7, 4th Street


Lot 1 through 7, 4th Street rear


Lot 19 roofing material on site,
Lot 18 roofing material on site, gable barge board complete,
Lot 17 gable barge board in progress
Lot 17-16 masonry party wall complete this day


Lot 17-16 party wall

Lot 20 through 26, 3rd Street rear
Lot 21 attic insulation
Lot 21 tub "P" trap fire saffing insulation
Lot 21 tub suround insulation at masonry wall inconsistent
Lot 21 tub "P" trap fire fire saffing insulation
Lot 21 2nd floor, drywall delivered
Lot 20, tub "P" trap fire saffing insulation
Lot 20, tub "P" trap fire saffing insulation, inconsistent insulation at exterior wall.

Lot 20 drywall delivered