Mid 80's F clear sky, 60's F overnight
Forecast 80's F with isolated showers and thunderstorms next 5 days.
Lots 20 through 26; front masonry in progress
Lots 1 through 7; front masonry on site, siding prep in progress, frame to masonry bolts in progress.
Site; excess excavated material removal in progress.
Lots 7 through 1, brick masonry delivered