Wednesday, August 13, 2008

Project Meeting Wednesday August 13, 2008

Wednesday August 13, 2008
Mid 80's F clear, 60's F overnight, rain earlier in the week.
Forecast 80's and 70's for next 5 days with possibility of showers.

46% complete, payment voucher approved and signed.

Attendance;
James Thomas; Union Square Homes
Harold Thomas; Union Square Homes
Jihad Ali ; Union Square Homes
Dan Thomer; WDC Construction
Lisa Gaffney; CEDA
Michael Washington; OHCD
John Paczewski; PHFA
Colin Dawson RA; CDRA
Kevin Maguire; for TRF
Harry Ackroyd; R&V for OHCD

Distribution all in attendance and;
David Collins; AICP, OHCD

Progress;
Lot 1; Main garage roof shingles complete, rough mechanicals in progress
Lot 2; Main garage roof shingles complete, rough mechanicals in progress
Lot 3; Main garage roof shingles complete, rough mechanicals in progress
Lot 4; Main garage roof shingles complete, rough mechanicals in progress
Lot 5; Main garage roof shingles complete, rough mechanicals in progress
Lot 6: Main garage roof shingles complete, rough mechanicals in progress
Lot 7; Main garage roof shingles complete, rough mechanicals in progress

Lot 8; Main garage roof shingles complete
Lot 9; Main garage roof shingles complete
Lot 10; Main garage roof shingles complete
Lot 11; Main garage roof shingles complete
Lot 12: Main garage roof shingles complete
Lot 13; Main garage roof shingles complete

Lot 14; Main garage roof shingles complete
Lot 15; Main garage roof shingles complete
Lot 16; Main garage roof shingles complete
Lot 17; Main garage roof shingles complete
Lot 18; Main garage roof shingles complete
Lot 19; Main garage roof shingles complete

Lot 20; Siding in progress, drywall hung and finished
Lot 21; Siding in progress, drywall hung and finished
Lot 22; Siding in progress, drywall hung and finish in progress
Lot 23; Siding in progress, rough mechanicls and air sealing complete
Lot 24; Rough mechanicals and air sealing complete
Lot 25; Rough mechanicals and air sealing complete
Lot 26; Rough mechanicals and air sealing complete

Anticipated Progress next week weather permitting;
Lots 1 through7; Siding complete, rough mechanicals complete
Lot 8 through 13; Siding in progress
Lot 14 through 19: Siding in progress
Lots 20 through 26; Siding complete, drywall complete

Project schedule to be prepared by WDC upon receipt of schedule for utility work;

Exterior Sheathing
Harry Ackroyd expressed concern on prolonged exposure of wall sheathing to UV and rain; house wrap and siding will continue without interuption until complete.

DELCORA
After this meeting Colin Dawson discussed with Ambric new request from DELCORA and Catania Engineering for City Engineer: show on drawing set existing sewer in 3rd and 4th Streets and sewer backflow preventer.

PECO
PECO gas service main from 2nd Street, street work commenced.



Prepared by Colin Dawson RA

Project photographs and Field Reports available at; http://unionsquarechesterpa.blogspot.com/


Jeffery Street at 4th Street
Lots 14 through 19, Union Street
Lots 20 through 26, 3rd Street rear
PECO gas work commenced Jeffery Street 3rd to 2nd Street
Lots 20 through 26, 3rd Street
Lots 1 through 7, 4th Street

Lot 20, drywall hung and finished
Lot 21, drywall hung and finished
Lot 22, drywall hung finish in progress
Lots 22, 21 & 23 siding in progress
Lots 8 through 13, Union Street