Thursday, August 28, 2008

Field Report Thursday August 28, 2008

Thursday August 28, 2008

Low 80's F, overcast and dry.
Isolated showers forecast for next few days from weakened TS Fay.

Lots 1 through 7; rough mechanicals complete, air sealing in progress

Lots 8 through 13; siding in progress

Lots 14 through 19; brick masonry in progress

Lots 20 through 26; porch footing in progress

Lot 22 porch footing
Lot 22 porch footing rebar grouted to house footing
Lot 26 through 20 porch footing excavation
Lot 8 through 13 siding in progress
Lots 13 through 8 siding in progress
Lots 13 through 8 brick masonry complete
Lots 19 through 14 brick masonry in progress
Lot 7 rough mechanical complete, air seal and fire stop in progress
Lot 6 rough mechanical complete, air seal and fire stop in progress
Lot 5 rough mechanical complete, air seal and fire stop in progress
Lot 4 rough mechanical complete
Lot 3 rough mechanical complete
Lot 2 rough mechanical complete
Lot 1 rough mechanical complete