Field Report Wednesday May 28, 2008

Mid 70's F clear, mid 50's overnight with light rain.

Lot 4 house slab complete, garage prep for pour
Lot 3 house slab complete, garage prep for pour
Lot 2 sub-slab plumbing
Lot 1 footing rebar set
Lot 5 & 6 foundation masonry in progress
Lot 7 footing excavation
Lot 8 roof truss install.
Crane loading roof truss.