Field Report 5-22-2008

Thursday 22nd May, 2008

Friday May, 16th, through Thursday May 22nd, 2008.

This week highs 60’s and 40’s during day, low 40’s to 50’s overnight, periods of heavy rain over the past weekend and occasional rain throughout the week. Periods of rain forecast for this coming weekend and next week with highs in the 80’s.


Progress; Friday 15th to Thursday 22th May, 2008
Lot 1;
excavation in progress
Lot 2;
slab prep in progress, living room slab poured
Utility pole rot and fractured, PECO replaced
Lot 3;
slab prep in progress, living room slab poured
Lot 4;
slab prep in progress, living room slab poured
Lot 5;
layout for foundation in progress
Lot 6:
layout for foundation in progress
Lot 7;
fill stock-pile removal in progress

Lot 8;
1st and 2nd floor framing complete, no new work, roof truss delivered
Lot 9;
1st and 2nd floor framing complete, no new work, roof truss delivered
Lot 10;
1st and 2nd floor framing complete, no new work, roof truss delivered
Lot 11;
1st and 2nd floor framing complete, no new work, roof truss delivered
Lot 12:
1st and 2nd floor framing complete, no new work, roof truss delivered
Lot 13;
1st and 2nd floor framing complete, no new work, roof truss delivered

Lot 14;
1st and 2nd floor framing complete, no new work, roof truss delivered
Lot 15;
1st and 2nd floor framing complete, no new work, roof truss delivered
Lot 16;
1st and 2nd floor framing complete, no new work, roof truss delivered
Lot 17;
1st and 2nd floor framing complete, no new work, roof truss delivered
Lot 18;
1st and 2nd floor framing complete, no new work, roof truss delivered
Lot 19;
1st and 2nd floor framing complete, no new work, roof truss delivered

Lot 20;
2nd floor framing in progress
Lot 21;
2nd floor framing in progress
Lot 22;
1st and 2nd floor framing complete
Lot 23;
1st and 2nd floor framing complete
Lot 24;
1st and 2nd floor framing complete
Lot 25;
1st and 2nd floor framing complete
Lot 26;
1st and 2nd floor framing complete


Anticipated Progress next week weather permitting;

Lots 2 through 4; slab pour in progress
Lot 1; prep for footing
Lot 5 & 6; footing concrete complete, foundation masonry in progress
Lots 20 & 21; framing complete

Roof truss in progress


Prepared by Colin Dawson RA