Thursday, May 15, 2008

Union Square Project Meeting





Thursday 15th May, 2008

Monday May, 12th, through Thursday May 15th, 2008.

This week highs to low 80’s and high 40’s during day, low 40’s to 50’s overnight, periods of heavy rain over the past weekend and Monday. Periods of rain forecast for this coming weekend and next week.

Attendance/Distribution;

Harold Thomas Union Square Homes
James Thomas Union Square Homes
Dan Thomer WDC Construction
Lisa Gaffney CEDA
Michael Washington OHCD
John Paczewski PHFA
Kevin Maguire for TRF
Colin Dawson RA CDRA


Progress; Monday 12th to 15th May, 2008
Lot 1;
excavation in progress
Lot 2;
sub-slab plumbing and slab prep in progress
Lot 3;
sub-slab plumbing and slab prep in progress
Lot 4;
sub-slab plumbing and slab prep in progress
Lot 5;
excavation in progress
Lot 6:
excavation in progress
Lot 7;
to be excavated (used as fill stock-pile)

Lot 8;
1st and 2nd floor framing complete, no new work, roof truss delivered
Lot 9;
1st and 2nd floor framing complete, no new work, roof truss delivered
Lot 10;
1st and 2nd floor framing complete, no new work, roof truss delivered
Lot 11;
1st and 2nd floor framing complete, no new work, roof truss delivered
Lot 12:
1st and 2nd floor framing complete, no new work, roof truss delivered
Lot 13;
1st and 2nd floor framing complete, no new work, roof truss delivered

Lot 14;
1st and 2nd floor framing complete, no new work, roof truss delivered
Lot 15;
1st and 2nd floor framing complete, no new work, roof truss delivered
Lot 16;
1st and 2nd floor framing complete, no new work, roof truss delivered
Lot 17;
1st and 2nd floor framing complete, no new work, roof truss delivered
Lot 18;
1st and 2nd floor framing complete, no new work, roof truss delivered
Lot 19;
1st and 2nd floor framing complete, no new work, roof truss delivered

Lot 20;
house slab complete this day, 1st and 2nd floor wall panels on site.
Lot 21;
house slab complete this day, 1st floor wall panels on site.
Lot 22;
1st and 2nd floor framing in progress
Lot 23;
1st and 2nd floor framing in progress
Lot 24;
1st and 2nd floor framing in progress
Lot 25;
1st and 2nd floor framing in progress
Lot 26;
1st and 2nd floor framing in progress


Anticipated Progress next week weather permitting;

Lots 2 through 4;
slab pour in progress
Lot 1;
footing concrete in progress
Lot 5, 6 & 7;
footing concrete in progress
Lots 20 through 26;
1st and 2nd floor framing complete

Work has been in progress from October 2007, under permits issued for house construction only.

INFRASTRUCTURE:
Site infrastructure including the storm water infiltration system has received a verbal agreement with DELCORA and the City Engineer, formal approval to follow.

Submissions have been made to the Chester Water Authority (CWA) for a new water main in Union Street.

Submissions for PECO gas and underground electric service have been made.

Submissions for Verizon Fios underground service have been made, all houses will be provided with a Fios panel from which the homeowner can contract with Verizon to provide; fiber-optic telephone, internet and television service.

The project schedule to completion is dependent upon a schedule to be developed with the underground utility providers; however the Union Square Homes (USH) anticipates a sample home completed by mid-July.

PAYMENT VOUCHER:
The payment voucher prepared by WDC was reviewed and approved. Two vouchers were prepared one for the work excluding site infrastructure items, and one for site infrastructure only. The infrastructure only voucher was prepared for information only and will not be submitted for review and approval until a formal approval has been issued for the infrastructure portion of the work.

MEETING SCHEDULE:
Voucher meetings will be held each month on a Wednesday at 1:00 PM, a meeting schedule is to be issued.

The meeting was adjourned.

Prepared by Colin Dawson RA



No comments: