Progress;
Lot 1; to be excavated (excavated library basement used as sump)
Lot 2; foundation masonry complete, back-fill in progress
Lot 3; foundation masonry complete, back-fill in progress
Lot 4; foundation masonry complete, back-fill in progress
Lot 5; to be excavated (used as fill stock-pile)
Lot 6: to be excavated (used as fill stock-pile)
Lot 7; to be excavated (used as fill stock-pile)

Lot 8; 1st and 2nd floor framing in progress
Lot 9; 1st and 2nd floor framing in progress
Lot 10; 1st and 2nd floor framing in progress
Lot 11; 1st and 2nd floor framing in progress
Lot 12: 1st and 2nd floor framing in progress
Lot 13; 1st and 2nd floor framing in progress

Lot 14; 1st and 2nd floor framing complete
Lot 15; 1st and 2nd floor framing complete
Lot 16; 1st and 2nd floor framing complete
Lot 17; 1st and 2nd floor framing complete
Lot 18; 1st and 2nd floor framing complete
Lot 19; 1st and 2nd floor framing complete

Lot 20; garage prep for pour
Lot 21; garage prep for pour
Lot 23; garage pour, sub-slab plumbing in progress
Lot 24; garage pour, sub-slab plumbing in progress
Lot 25; garage pour, kitchen/den slab prep for pour
Lot 26; garage pour, kitchen/den slab prep for pour

Anticipated Progress next week weather permitting;

Lots 2 through 4; sub-slab plumbing in progress
Lots 8 through 13; 1st and 2nd floor framing complete
Lots 14 through 19; WDC framing punch-list items
Lots 20 through 23; garage pour, sub-slab plumbing in progress.
Lots 24 through 26 1st and 2nd floor framing in progress