Monday May, 5th, through Friday May 9th, 2008.

This week highs to low 80’s and high 50’s during day, low 40’s to 50’s overnight, periods of rain Thursday and all day Friday through Saturday. Periods of rain forecast for next week.


Progress;
Lot 1; excavation in progress
Lot 2; sub-slab plumbing and slab prep in progress
Lot 3; sub-slab plumbing and slab prep in progress
Lot 4; sub-slab plumbing and slab prep in progress
Lot 5; excavation in progress
Lot 6: to be excavated (used as fill stock-pile)
Lot 7; to be excavated (used as fill stock-pile)

Lot 8; 1st and 2nd floor framing complete
Lot 9; 1st and 2nd floor framing complete
Lot 10; 1st and 2nd floor framing complete
Lot 11; 1st and 2nd floor framing complete
Lot 12: 1st and 2nd floor framing complete
Lot 13; 1st and 2nd floor framing complete

Lot 14; 1st and 2nd floor framing complete, no new work
Lot 15; 1st and 2nd floor framing complete, no new work
Lot 16; 1st and 2nd floor framing complete, no new work
Lot 17; 1st and 2nd floor framing complete, no new work
Lot 18; 1st and 2nd floor framing complete, no new work
Lot 19; 1st and 2nd floor framing complete, no new work

Lot 20; garage and living room poured prep for kitchen pour,
1st floor panels on site.
Lot 21; garage and living room poured prep for kitchen pour,
1st floor panels on site.
Lot 22; house slab complete, 1st floor wall panels on site.
Lot 23; house slab complete, 1st floor wall panels on site.
Lot 24; house slab complete, 1st floor wall panels on site.
Lot 25; house slab complete, 1st floor wall panels on site.
Lot 26; house slab complete, 1st floor wall panels on site.


Anticipated Progress next week weather permitting;

Lots 2 through 4; slab pour in progress
Lot 1; excavation complete
Lot 5, 6 & 7; excavation in progress
Lots 20 & 21 house slab complete
Lots 22 through 26; 1st floor framing in progress