Friday, June 6, 2008

Field Report Friday June 6, 2008

Friday June 6, 2008, mid 80's humid.
Forecast next 5 days in high 90's and humid with thunderstorms mid week.

Lot 1 ready for living room and garage slab, party wall masonry in progress
Lot 2 party wall masonry complete to 2nd floor bond beam

Lot 3 party wall masonry complete to bond beam
Lot 4 party wall masonry complete to bond beam
Lot 5 sub slab prep in progress
Lots 8 though 14, 2nd floor and attic party wall masonry delivered, for work next week. #4 bar vertical reinforcing to be epoxy anchored into bond beam at 32" o.c.
2nd floor top hung joist hangers to be installed at all mutiple joist locations including triple joist at masonry party wall.

No comments:

Post a Comment