Tuesday, June 24, 2008

Field Report Tuesday June 24, 2008

Tuesday June 24, 2008.
Low 8o's F, 60's F overnight, 80's to 90's forecast for the week with possibility of thunderstorms.

Lot 20 through 26;
Roof shingles in progress,
Interior Sanitary plumbing commenced lot 20,
Ductwork material for 20 through 26 of loading in progress,
Electric device boxes installation 20 through 26 in progress,

Lots 1 through 7
1st floor framing complete
2nd floor framing in progress.

3rd Street at Jeffery Street
Jeffery Street at 4th Street
4th Street at Jeffery Street
Yarnall Street at 4th Street
4th Street and Union Street rear at Yarnall Street
Union Street at Yarnall Street
3rd Street and Union Street rear at Yarnall Street
3rd Street at Yarnall Street
Lot 26 roof material loading
Lot 26 2nd floor electric device boxes
Lot 26 interior sanitary plumbing in progress
Lot 24 garage roof shingles, and step flashing
Lot 24 attic access hatch framing
Lot 24 stair and electric device boxes
Lot 25 roof shingle in progress