Thursday, June 12, 2008

Project meeting June 11, 2008

Wednesday June 11, 2008

Thursday May 22, through Wednesday June 11, 2008.

This week highs 90’s and 80’s during day with thunder storms, 90’s to 70’s overnight. Showers and thunder storms forecast for coming weekend, next weeks highs in the 80’s.

26.40% complete

Attendance;

James Thomas; Union Square Homes
Dan Thomer; WDC Construction
Lisa Gaffney; CEDA
Michael Washington; OHCD
John Paczewski; PHFA
Kevin Maguire; for TRF
Colin Dawson RA; CDRA

Distribution;

all in attendance
Harold Thomas; Union Square Homes
David Collins AICP, OHCD
Harry Ackroyd

Progress;

Lot 1;
party wall masonry to 2nd floor, living room and garage slab complete, 1st floor wall panels on site

Lot 2;
party wall masonry to 2nd floor, house slab complete, 1st floor wall panels on sites

Lot 3;
party wall masonry to 2nd floor, house slab complete, 1st floor wall panels on sites

Lot 4;
party wall masonry to 2nd floor, house slab complete, 1st floor wall panels on sites

Lot 5;
living room and garage slab complete,

Lot 6:
living room and garage slab complete,

Lot 7;
living room and garage slab complete,

Lot 8;
main roof truss installed, no front gable

Lot 9;
main roof truss installed, no front gable

Lot 10;
main roof truss installed, no front gable

Lot 11;
main roof truss installed, no front gable

Lot 12:
main roof truss installed, no front gable

Lot 13;
main roof truss installed, no front gable,

Lot 14;
main roof truss and sheathing installed, no front gable

Lot 15;
main roof truss and sheathing installed, no front gable

Lot 16;
main roof truss and sheathing installed, no front gable

Lot 17;
main roof truss and sheathing installed, no front gable

Lot 18;
main roof truss and sheathing installed, no front gable

Lot 19;
main roof truss and sheathing installed, no front gable

Lot 20;
main roof and front gable truss and sheathing complete, garage truss and sheathing installed

Lot 21;
main roof and front gable truss and sheathing complete, party wall masonry to lot 20 complete to roof sheathing

Lot 22;
main roof and front gable truss and sheathing complete, party wall masonry to lot 21 complete to roof sheathing

Lot 23;
main roof and front gable truss and sheathing complete, lot 22-23 party wall masonry in progress

Lot 24;
main roof and front gable truss and sheathing complete

Lot 25;
main roof and front gable truss and sheathing complete, party wall masonry to lot 26 complete, garage roof truss and sheathing in progress

Lot 26;
main roof and front gable truss and sheathing complete, garage roof truss and sheathing installed


Anticipated Progress next week weather permitting;


Lots 1, 5, 6 & 7;
sub-slab plumbing complete, slab pour complete, masonry party wall to 2nd floor complete

Lot 8 through 13;
roof sheathing and front gable complete

Lot 14 through 19:
front gable complete

Lots 20 through 26;
party wall masonry complete, garage roof complete


Prepared by Colin Dawson RA





4th and Jeffery Street Lot 1 through 7
4th and Yarnall Street lots 7 through 1

Union Street lots 19 through 14
Union Street lots 8 through 13
3rd and Yarnall Street lots 26 through 20
Lot 23-24 party wall in progress
Lot 23-24 part wall in progress
Lot 20 garage
Lot 7 living room slab poured, garage slab ready for pour
Lot 1 through 7 1st floor wall panels delivered