Field Report Monday June 9, 2008
Monday June 9, 2008; mid 90's F less humid.
Party wall masonry to roof lots 20 through 26 in progress
Lot 5 living room slab complete
Lot 6 living room slab ready for pour, garage slab complete
Lot 7 garage slab ready for pour
Lot 20 t0 21 party wall to roof in progress
Lot 25 to 26 party wall to roof complete
No comments:
Post a Comment
Newer Post
Older Post
Home
Subscribe to:
Post Comments (Atom)
Check your car radio weather setting for latest information from NWS All Hazards
Chester Weather Forecast NWS
Archive
►
2009
(72)
►
November
(1)
►
October
(4)
►
September
(5)
►
August
(10)
►
July
(9)
►
June
(7)
►
May
(7)
►
April
(7)
►
March
(6)
►
February
(7)
►
January
(9)
▼
2008
(92)
►
December
(14)
►
November
(12)
►
October
(17)
►
September
(10)
►
August
(10)
►
July
(10)
▼
June
(12)
Field Report Thursday June 26, 2008 Lateral Force ...
Field Report Tuesday June 24, 2008
Field Report Thursday June 19, 2008
Field Report June 19, 2008 Building Structural System
Field Report Wednesday June 18, 2008 Wall Collapse
Field Report Wednesday June 18, 2008
Field Report Friday June 13, 2008
Project meeting June 11, 2008
Field Report Monday June 9, 2008
Field Report Friday June 6, 2008
Field Report June 4, 2008
Field report June 2, 2008
►
May
(7)
City Engineer Required Submittals (Partial) From GC
Revised Site Engineering Drawings
Material and Component Certification from Manufacturer and Contractor
Material and Component Manufacturer Test Data
Substantial Complete Check List To Be Complted by GC
Punch list item completion schedule
Energy Star Certificate
Homeowner maintenance and warranty binder
Permit offical issued Certificate of Occupancy
GC certification statement of conformance with permit approved drawings
Record drawing set with GC mark-ups
Followers
No comments:
Post a Comment