60's F dry, forecast 60's and 50's next 5 days and dry.
Porch roof framing lots 1 through 6 and 20 through 22 in progress, end non-bearing drop soffit to be installed.
3rd Street excavated for curb.
4th Street sewer to main in progress.
Union Street excavate to rough sub-paving grade in progress. Union Street sewer work after 4th Street sewer complete.
No comments:
Post a Comment