Friday, October 31, 2008

Field Report Friday October 31, 2008

Friday October 31, 2008
60's F dry, forecast 60's and 50's next 5 days and dry.

Porch roof framing lots 1 through 6 and 20 through 22 in progress, end non-bearing drop soffit to be installed.

3rd Street excavated for curb.

4th Street sewer to main in progress.

Union Street excavate to rough sub-paving grade in progress. Union Street sewer work after 4th Street sewer complete.

Lot 20, 21 & 22 porch framing
4th and Jeffery sewer work
4th and Jeffery sewer work



4th and Jeffery sewer work