Thursday, October 9, 2008

Project Meeting Wednesday October 8, 2008

Project Meeting Wednesday Ocotber 8, 2008

70's F overcast, 40's F overnight, showers forecast for overnight.
Forecast low 70's for next 5 days and dry.


59% complete, payment voucher approved and signed

Attendance;
James Thomas; Union Square Homes
Harold Thomas; Union Square Homes
Jihad Ali ; Union Square Homes
Dan Thomer; WDC Construction
Michael Washington; OHCD
Harry Ackroyd; R&V for OHCD
Kevin Maguire; for TRF
Colin Dawson RA; CDRA
John Paczewski; PHFA


Distribution all in attendance and;
Assistant Director, Linda Hill; OHCD
Lisa Gaffney; CEDA

Progress;

4th Street
Lot 1; Drywall hung, finish in progress, porch footing in progress
Lot 2; Drywall hung, finish in progress, porch footing in progress
Lot 3; Drywall hung, finish in progress, porch footing in progress
Lot 4; Drywall hung, finish in progress, porch footing in progress
Lot 5; Drywall hung, finish in progress, porch footing in progress
Lot 6: Drywall hung, finish in progress, porch footing in progress
Lot 7; Drywall hung, finish in progress, porch footing in progress

Union Street, north side;
Lot 8; Porch footing complete.
Lot 9; Porch footing complete.
Lot 10; Porch footing complete.
Lot 11; Porch footing complete.
Lot 12: Porch footing complete.
Lot 13; Porch footing complete.

Union Street, south side;
Lot 14: Rough mechanicals in progress, porch footing poured.
Lot 15; Rough mechanicals in progress, porch footing poured.
Lot 16; Rough mechanicals in progress, porch footing poured.
Lot 17; Rough mechanicals in progress.
Lot 18; Rough mechanicals in progress.
Lot 19; Rough mechanicals in progress.

3rd Street;
Lot 20; Finish paint in progress, kitchen cabinet and vanity installed, light fixtured installed, furnace and HWH installed.
Lot 21; Finish paint in progress, kitchen cabinet and vanity installed, light fixtured installed, furnace and HWH installed.
Lot 22; Finish paint in progress, kitchen cabinet and vanity installed, light fixtured installed, furnace and HWH installed.
Lot 23; Finish paint in progress.
Lot 24; Finish paint in progress.
Lot 25; Trim in progress.
Lot 26; Trim in progress.

Anticipated Progress next week weather permitting;
Lots 1 through7; Prime paint in progress, porch masonry in progress
Lot 8 through 13; Porch masonry in progress.
Lot 14 through 19: Rough mechanicals in progress, porch footing in progress.
Lots 20 through 26; Kitchens and finishes in progress, porch slab in progress

DELCORA
Sewer connection permit fee paid, awaiting issuance for sewer connection permit.

DCPD
DELCORA signed-off "project planning module", planning module submitted to Delaware County Planning Department for review.

PECO
PECO coordinating with Dan Thomer, gas and electric to be installed after sewer, Verizon coordinating with PECO.

CWA
Chester Water Authority coordinating with Dan Thomer, water service and meters after sewer installed.

HC Accessible Units
Colin Dawson, James Thomas, Century 21 Alliance and prospective Homeowner for Lot 25 met on site. The homeowner has limitation on upper body reach; homeowner requested grab bars in 1st floor bathroom, but no changes to the kitchen.

Next project meeting 2nd, or 3rd Wednesday of November, to be confirmed.

Prepared by Colin Dawson RA, images and field reports available at http://www.unionsquarechesterpa.blogspot.com/

Lot 20
Lot 20
Lot 21
Lot 21
Lot 22
Lot 22
Lot 23
Lot 23
Lot 24
Lot 24
Lot 25
Lot 25
Lot 26
Lot 26

Lot 13 through 8
Lot 8 though 13
Lot 14 through 19
Lot 1
Lot 2
Lot 3
Lot 4
Lot 5
Lot 6
Lot 7
Lot 7
Lots 1 through 7
Lot 1
Lot 3, 2 & 1
Lot 4