Thursday, October 30, 2008

Field Report Thursday October 30, 2008

Thursday October 30, 2008
40's F during day, 30's F overnight dry.
Forecast 60's and 50's next 5 days dry.

3rd Street curb excavation in progress, lots 20 through 26
4th Street sewer installed, back fill after soil dries, lots 1 through 7
4th Street porch framing in progress, lots 1 through 6.

3rd Street curb excavation
4th Street sewer, manhole at 4th and Jeffery
4th Street porch in progress