Monday, October 6, 2008

Field Report Monday October 6, 2008

Monday October 6, 2008
60's F overcast, 40'sF overnight
Showers forecast for later in the week.

Lots 14 through 19 porch footing excavation in progress
Lots 8 through 13 duct cut-out commenced without header installed.Typical correct installation at kitchen-living room passage header, with 4" PVC and ductwork.
Lot 7 back-order one piece shower/tub installed, drywall on site
Lot 6 drywall kinish in progress
Lot 5 drywall finish in progress
Lot 4 drywall finish in progress
Lot 3 drywall finish in progress
Lot 2 drywall finish in progress
Lot 1 drywall finish in progress