Thursday October 16, 2008
High 70's F during day, 60's F overnight, dry.
Forecast next 5 days, 60's F dry, chance of showers mid week.
Lots 1 through 7; prep for porch slab, trim in progress.
Lots 8 through 13; ductwork in progress.
Lots 14 through 19; kitchen ceiling framing in progress.
Lots 20 through 26; 3rd Street sewer work commenced.
Billadelphia requested revision to end of run manhole invert, sewer slope and requested sewer located midway between curb and porch to clear PECO pole bearing soil. Jim Morris DELCORA contacted, OK for revision on 10-17-2008.
Lots 1 through 7 porch slab prep
Lot 1 trim on site
Lot 2 trim on site