Monday, October 13, 2008

Field Report Monday October 13, 2008

Monday October 13, 2008
High 70's F, 50's F overnight dry
Forecast for next 5 days, high 70's F dropping to 60's F with showers towards end of the week.

Sewer Connection Permit issued.
PECO relocated/replaced two poles on 3rd Street.
Site clean-up and prep for sewer installation later in week.


Lots 1 through 7 porch foundation masonry
4th Street rear, lots 1 through 7 and 8 through 13
Lots 8 through 13 porch foundation masonry
Lots 14 through 19 porch foundation masonry
3rd Street rear, Lots 14 through 19 and 20 through 26
Lots 20 through 26 porch slab to be poured before sewer installation.