Monday, October 20, 2008

Field Report Monday October 20, 2008

Monday October 20, 2008
60's F during day, 40's F overnight.
Forecast 50's and 60's and dry next 5 days


Lot 1 interior doors on site
Lot 2 trim in progress
Lot 3 trim complete
Lot 4 trim complete
Lot 5 trim complete
Lot 6 trim complete
Lot 7 trim on site
Lot 7 prep for porch, 1 through 6 porch slab complete
Lot 13 rough plumbing in progress
Lot 12 & 13 prep for porch concrete in progress
Lot 20 through 26 sewer in progress 3rd Street
Lot 26 sewer trap and vent
Lot 25 sewer trap and vent in progress