Monday October 20, 2008
60's F during day, 40's F overnight.
Forecast 50's and 60's and dry next 5 days

 Lot 1 interior doors on site

 Lot 2 trim in progress

 Lot 3 trim complete

 Lot 4 trim complete

 Lot 5 trim complete

 Lot 6 trim complete

 Lot 7 trim on site

 Lot 7 prep for porch, 1 through 6 porch slab complete

 Lot 13 rough plumbing in progress

 Lot 12 & 13 prep for porch concrete in progress

 Lot 20 through 26 sewer in progress 3rd Street

 Lot 26 sewer trap and vent

 Lot 25 sewer trap and vent in progress