Friday, October 31, 2008

Field Report Friday October 31, 2008

Friday October 31, 2008
60's F dry, forecast 60's and 50's next 5 days and dry.

Porch roof framing lots 1 through 6 and 20 through 22 in progress, end non-bearing drop soffit to be installed.

3rd Street excavated for curb.

4th Street sewer to main in progress.

Union Street excavate to rough sub-paving grade in progress. Union Street sewer work after 4th Street sewer complete.

Lot 20, 21 & 22 porch framing
4th and Jeffery sewer work
4th and Jeffery sewer work



4th and Jeffery sewer work

Thursday, October 30, 2008

Field Report Thursday October 30, 2008

Thursday October 30, 2008
40's F during day, 30's F overnight dry.
Forecast 60's and 50's next 5 days dry.

3rd Street curb excavation in progress, lots 20 through 26
4th Street sewer installed, back fill after soil dries, lots 1 through 7
4th Street porch framing in progress, lots 1 through 6.

3rd Street curb excavation
4th Street sewer, manhole at 4th and Jeffery
4th Street porch in progress

Wednesday, October 29, 2008

Field Report Wednesday October 29, 2008

Wednesday October 29, 2008
50's F and 40,s F overcast, heavy rain Monday through Tuesday with winds gusting to 40 mph on Tuesday. Forecast 60's and 50's next few days dry.

Lot 20, 21 & 22 porch in progress

Lot 20, 21 & 22





Monday, October 27, 2008

Field Report Monday October 27, 2008

Monday Octobet 27, 2008
60's F during day 40's F overnight, rain over the weekend.
Forecast 50's and 60's next 5 days with showers, dry for second half of the week.

Infrasource on site to review location of service trench.

Lot 7, 4th and Yarnall Street sewer manhole
4th Street sewer trench in progress
4th Street at Jeffery Street

Thursday, October 23, 2008

Field Report Thursday October 23, 2008

Thursday October 23, 2008

50's F during day, 40's F overnight dry.


3rd Street sewer extended to 24" brick sewer in Jeffery Street with DELCORA on site review

Wednesday, October 22, 2008

Field Report Wednesday October 22, 2008

Wednesday October 22, 2008
50's F during day, 40's F overnight dry.
Forecast 50's and 40's next 5 days with chance of rain at the weekend.


Lot 8 rough mechanicals in progress
Lot 9 rough mechanical in progress
Lot 10 rough mechanical in progress
Lot 11 rough mechanical in progress
Lot 12 rough mechanical in progress
Lot 13 rough mechanical in progress
Lot 20 through 26, 3rd Street sewer back-fill
Lot 26 finish paint and light fixtures
Lot 25 finish paint and light fixtures
Lot 24 finish paint and light fixtures
Lot 23 finish paint and light fixtures
Lot 22 finish paint and light fixtures
Lot 21 finish paint and light fixtures
Lot 20 finish paint and light fixtures

Tuesday, October 21, 2008

Field Report Tuesday October 21, 2008

Tuesday October 21, 2008

60's F during day, 40's F overnight, dry. Forecast 50's and 60's next 5 days with chance of showers at weekend.


Lot 20 through 26, 3rd Street sewer complete (except new manhole at 3rd and Jeffery), water service run to meter location at curb, back-fill in progress.

CWA on-site, discuss with Billadelphia; 3rd Street curb installed this week, CWA to run service and install meters next week. 4th Street sewer and curb complete next week and CWA to install water service and meters the following week.

Lot 20 through 26, 3rd Street sewer
Lot 26, 3rd and Yarnall manhole

Monday, October 20, 2008

Field Report Monday October 20, 2008

Monday October 20, 2008
60's F during day, 40's F overnight.
Forecast 50's and 60's and dry next 5 days


Lot 1 interior doors on site
Lot 2 trim in progress
Lot 3 trim complete
Lot 4 trim complete
Lot 5 trim complete
Lot 6 trim complete
Lot 7 trim on site
Lot 7 prep for porch, 1 through 6 porch slab complete
Lot 13 rough plumbing in progress
Lot 12 & 13 prep for porch concrete in progress
Lot 20 through 26 sewer in progress 3rd Street
Lot 26 sewer trap and vent
Lot 25 sewer trap and vent in progress

Friday, October 17, 2008

Field Report Friday October 17, 2008

Friday October 17, 2008
60's F during day, 40'sF overnight, dry



Lot 1, 2 & 3 porch slab poured.

3rd Street sewer in progress, 3rd Street curb removed.

4th Street lot 1, 2 & 3 porch slab
Sewer manhole set 3rd and Yarnall
Precast sewer manhole

Field Report Thursday October 16, 2008

Thursday October 16, 2008
High 70's F during day, 60's F overnight, dry.
Forecast next 5 days, 60's F dry, chance of showers mid week.

Lots 1 through 7; prep for porch slab, trim in progress.

Lots 8 through 13; ductwork in progress.

Lots 14 through 19; kitchen ceiling framing in progress.

Lots 20 through 26; 3rd Street sewer work commenced.
Billadelphia requested revision to end of run manhole invert, sewer slope and requested sewer located midway between curb and porch to clear PECO pole bearing soil. Jim Morris DELCORA contacted, OK for revision on 10-17-2008.

Lots 1 through 7 porch slab prep
Lot 1 trim on site
Lot 2 trim on site
Lot 3 trim in progress
Lot 4 trim in progress
Lot 5 trim in progress
Lot 6 trim in progress
Lot 7 trim in progress
Lot 8 duct in progress
Lot 9 duct in progress
Lot 10 duct in progress
Lot 11 duct in progress
Lot 12 duct in progress