Friday October 31, 2008
60's F dry, forecast 60's and 50's next 5 days and dry.
Porch roof framing lots 1 through 6 and 20 through 22 in progress, end non-bearing drop soffit to be installed.
3rd Street excavated for curb.
4th Street sewer to main in progress.
Union Street excavate to rough sub-paving grade in progress. Union Street sewer work after 4th Street sewer complete.
Lot 20, 21 & 22 porch framing
Friday, October 31, 2008
Thursday, October 30, 2008
Field Report Thursday October 30, 2008
Thursday October 30, 2008
40's F during day, 30's F overnight dry.
Forecast 60's and 50's next 5 days dry.
3rd Street curb excavation in progress, lots 20 through 26
4th Street sewer installed, back fill after soil dries, lots 1 through 7
4th Street porch framing in progress, lots 1 through 6.
3rd Street curb excavation
40's F during day, 30's F overnight dry.
Forecast 60's and 50's next 5 days dry.
3rd Street curb excavation in progress, lots 20 through 26
4th Street sewer installed, back fill after soil dries, lots 1 through 7
4th Street porch framing in progress, lots 1 through 6.
3rd Street curb excavation
Wednesday, October 29, 2008
Field Report Wednesday October 29, 2008
Monday, October 27, 2008
Field Report Monday October 27, 2008
Monday Octobet 27, 2008
60's F during day 40's F overnight, rain over the weekend.
Forecast 50's and 60's next 5 days with showers, dry for second half of the week.
Infrasource on site to review location of service trench.
Lot 7, 4th and Yarnall Street sewer manhole
4th Street sewer trench in progress
4th Street at Jeffery Street
60's F during day 40's F overnight, rain over the weekend.
Forecast 50's and 60's next 5 days with showers, dry for second half of the week.
Infrasource on site to review location of service trench.
Lot 7, 4th and Yarnall Street sewer manhole
4th Street sewer trench in progress
4th Street at Jeffery Street
Thursday, October 23, 2008
Field Report Thursday October 23, 2008
Wednesday, October 22, 2008
Field Report Wednesday October 22, 2008
Wednesday October 22, 2008
50's F during day, 40's F overnight dry.
Forecast 50's and 40's next 5 days with chance of rain at the weekend.
Lot 8 rough mechanicals in progress
Lot 9 rough mechanical in progress
Lot 10 rough mechanical in progress
Tuesday, October 21, 2008
Field Report Tuesday October 21, 2008
Tuesday October 21, 2008
Lot 26, 3rd and Yarnall manhole
60's F during day, 40's F overnight, dry. Forecast 50's and 60's next 5 days with chance of showers at weekend.
Lot 20 through 26, 3rd Street sewer complete (except new manhole at 3rd and Jeffery), water service run to meter location at curb, back-fill in progress.
CWA on-site, discuss with Billadelphia; 3rd Street curb installed this week, CWA to run service and install meters next week. 4th Street sewer and curb complete next week and CWA to install water service and meters the following week.
Lot 20 through 26, 3rd Street sewerLot 26, 3rd and Yarnall manhole
Monday, October 20, 2008
Field Report Monday October 20, 2008
Friday, October 17, 2008
Field Report Friday October 17, 2008
Field Report Thursday October 16, 2008
Thursday October 16, 2008
High 70's F during day, 60's F overnight, dry.
Forecast next 5 days, 60's F dry, chance of showers mid week.
Lots 1 through 7; prep for porch slab, trim in progress.
Lots 8 through 13; ductwork in progress.
Lots 14 through 19; kitchen ceiling framing in progress.
Lots 20 through 26; 3rd Street sewer work commenced.
Billadelphia requested revision to end of run manhole invert, sewer slope and requested sewer located midway between curb and porch to clear PECO pole bearing soil. Jim Morris DELCORA contacted, OK for revision on 10-17-2008.
Lots 1 through 7 porch slab prep
Lot 1 trim on site
Lot 2 trim on site
High 70's F during day, 60's F overnight, dry.
Forecast next 5 days, 60's F dry, chance of showers mid week.
Lots 1 through 7; prep for porch slab, trim in progress.
Lots 8 through 13; ductwork in progress.
Lots 14 through 19; kitchen ceiling framing in progress.
Lots 20 through 26; 3rd Street sewer work commenced.
Billadelphia requested revision to end of run manhole invert, sewer slope and requested sewer located midway between curb and porch to clear PECO pole bearing soil. Jim Morris DELCORA contacted, OK for revision on 10-17-2008.
Lots 1 through 7 porch slab prep
Lot 1 trim on site
Lot 2 trim on site
Subscribe to: